The Utilities Contracts (Scotland) Regulations 2016, Cross Heading: SECTION 1 is up to date with all changes known to be in force on or before 06 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
15.—(1) These Regulations apply to a procurement where the estimated value of the contract to be awarded (not including VAT) is equal to or greater than—
(a)in the case of a supply or service contract or design contest, [F1£378,660];
(b)in the case of a works contract, [F2£4,733,252];
(c)in the case of a contract for a service listed in Schedule 2 (social and other specified services), [F3£884,720].
(2) Where proposed works, acquisition of supplies or provision of services may be procured in the form of separate lots these Regulations do not apply to the award of a contract for a lot where—
(a)the estimated value of that lot is less than—
(i)[F4£70,778], in the case of supplies or services; or
(ii)[F5£884,720], in the case of works; and
(b)the estimated total aggregate value of all such lots to be awarded without application of these Regulations does not exceed 20% of the estimated aggregate value of all the lots calculated in accordance with regulation 16 (methods for calculating the estimated value).
F6(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(4) In this regulation reference to a “contract” includes reference to a framework agreement, dynamic purchasing system and design contest.
Textual Amendments
F1Sum in reg. 15(1)(a) substituted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(6)(a) (with sch. paras. 1-5)
F2Sum in reg. 15(1)(b) substituted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(6)(b) (with sch. paras. 1-5)
F3Sum in reg. 15(1)(c) substituted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(6)(c) (with sch. paras. 1-5)
F4Sum in reg. 15(2)(a)(i) substituted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(6)(d)(i) (with sch. paras. 1-5)
F5Sum in reg. 15(2)(a)(ii) substituted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(6)(d)(ii) (with sch. paras. 1-5)
F6Reg. 15(3) omitted (31.12.2020) by virtue of The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(6)(e) (with sch. paras. 1-5)
Commencement Information
15A.—(1) Every two years the Scottish Ministers must review the thresholds specified in regulation 15(1)(a) and (b) (“the reviewable thresholds”) to verify whether they correspond with the thresholds established for those purposes in the GPA.
(2) The Scottish Ministers must do so by calculating the sterling value of each of the reviewable thresholds on the basis of the average daily value of sterling in terms of the special drawing rights mentioned in the GPA over a period of 24 months ending with 31 August.
(3) The Scottish Ministers must make that calculation using the applicable conversion rates in the monthly International Financial Statistics published from time to time by the International Monetary Fund.
(4) If the sterling value of a reviewable threshold so calculated differs from the sum for the time being set by regulation 15(1) in respect of that threshold, the Scottish Ministers must make regulations amending regulation 15(1) so as to substitute for that sum the sum equal to that value.
(5) Such regulations—
(a)must be made and laid before the Scottish Parliament before 1 November following the end of the 24 month period covered by the review, and
(b)must provide for the substitution to come into force on the following 1 January.
(6) The first review under this regulation must relate to the 24 month period ending with 31 August 2021.]
Textual Amendments
F7Reg. 15A inserted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(7) (with sch. paras. 1-5)
16.—(1) A utility must calculate the estimated value of a contract by reference to the total amount payable under it (regardless of the form of such payment), not including VAT.
(2) The total amount payable includes the amount payable as a result of the exercise of any form of option and any renewal of the contract as explicitly set out in the procurement documents.
(3) Where a utility provides for prizes or payments to candidates or tenderers it must take them into account when calculating the estimated value.
(4) Where a utility is comprised of separate operational units the utility—
(a)may calculate the estimated value by reference to each such unit or certain category thereof where that unit or certain category thereof is independently responsible for its procurement; and
(b)must calculate the estimated value by reference to the total for all the operational units which are not so responsible.
(5) A utility must not choose a method to be used to calculate the estimated value of a contract with the intention of excluding the contract from the application of these Regulations.
(6) A utility must not sub-divide a contract with the effect of excluding the contract from the application of these Regulations unless such sub-division is justified by objective reasons.
(7) The estimated value must be the value estimated at the moment at which the procurement is commenced.
(8) In the case of a framework agreement or dynamic purchasing system the estimated value shall be the total estimated value of all of the contracts envisaged pursuant to and for the total term of the agreement or system.
(9) In the case of an innovation partnership the estimated value shall be the total estimated value of the research and development activities to take place during all stages of the partnership together with the estimated value of works, supplies or services to be developed and delivered by the partner.
(10) In the case of a works contract the estimated value shall include the total estimated value of any supplies and services that are necessary for executing the works and are to be provided by the utility to the contractor.
(11) In the case of a works or service contract to be awarded in the form of separate lots, the estimated value shall be the total estimated value of all such lots.
(12) In the case of a contract for supplies which may be awarded in the form of separate lots the estimated value shall be the total estimated value of all such lots and these Regulations apply to each lot accordingly where the aggregate value of the lots is equal to or greater than the relevant threshold referred to in regulation 15 (thresholds).
(13) In the case of supply or service contracts which are regular in nature or which are intended to be renewed in a given period, the estimated value shall be calculated by reference to—
(a)the total actual value of contracts of the same type awarded during the period of 12 months or the financial year preceding the proposed award of a further contract but with adjustment of such value, where possible, to take account of the changes in quantity or value which the utility considers likely to occur during the period of 12 months following the award of the contract; or
(b)the total estimated value of the successive contracts awarded during the 12 months following the first delivery, or during the financial year.
(14) In the case of a supply contract relating to the leasing, rental, hire or hire purchase of products the estimated value shall be—
(a)in the case of a fixed term contract for a period of less than or equal to 12 months, the total estimated value of the contract;
(b)in the case of a fixed term contract for a period of more than 12 months, the total value including the estimated residual value; and
(c)in the case of a contract without a fixed term or the term of which cannot be defined, the monthly value multiplied by 48.
(15) In the case of a service contract for a service of a kind mentioned herein, the estimated value shall be calculated by reference to—
(a)for insurance services, the premium payable and any other form of remuneration;
(b)for banking and other financial services, the fees, commissions payable, interest and any other form of remuneration; and
(c)for design contracts, the fees, commissions payable and any other form of remuneration.
(16) In the case of a service contract which does not indicate a total price, the estimated value must be calculated by reference to—
(a)in the case of a contract for a fixed term of less than or equal to 48 months, the total value of the contract for its full term; and
(b)in the case of a contract for a term of more than 48 months or a contract without a fixed term, the monthly value multiplied by 48.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: