The Utilities Contracts (Scotland) Regulations 2016, SUB-SECTION 1 is up to date with all changes known to be in force on or before 29 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
75.—(1) A utility may establish and operate a system of qualification of economic operators.
(2) A utility which establishes or operates a system of qualification must ensure that economic operators are at all times able to request qualification.
(3) The system under paragraph (1) may involve different qualification stages.
(4) A utility must establish objective rules and criteria for—
(a)the exclusion and selection of economic operators requesting qualification; and
(b)the operation of the qualification system, covering matters such as—
(i)inscription in the system;
(ii)periodic updating of the qualifications, if any; and
(iii)the duration of the system.
(5) Where the rules and criteria referred to in paragraph (4) include technical specifications, regulations 58 to 60 apply.
(6) The rules and criteria referred to in paragraph (4)—
(a)must be made available to economic operators upon request; and
(b)may be updated as required and, if so, must be communicated to interested economic operators.
(7) Where a utility considers that the qualification system of certain other entities or other bodies meets its requirements, it must communicate the names of those entities and bodies to interested economic operators.
(8) A utility must keep a written record of qualified economic operators, which may be divided into categories according to type of contract for which the qualification is valid.
(9) When a call for competition is made by means of a notice on the existence of a qualification system, specific contracts for the works, supplies or services covered by the qualification system must be awarded by restricted or negotiated procedure, competitive dialogue or innovation partnership as modified so that all tenderers and participants are selected among the candidates already qualified in accordance with such a system without being required to submit further information for qualitative selection or to submit a request to participate.
(10) Any charges that are billed to an economic operator by a utility in connection with requests for qualification or with updating or conserving an already obtained qualification in accordance with the system must be proportionate to the generated costs.
76.—(1) A utility—
(a)may establish objective rules and criteria for the exclusion and selection of tenderers or candidates; and
(b)if so, must make those rules and criteria available to interested economic operators.
(2) Subject to paragraph (3), where a utility needs to ensure an appropriate balance between the particular characteristics of the procurement and the resources required to conduct it, it may, in restricted procedures, negotiated procedures, competitive dialogues or innovation partnerships, establish objective rules and criteria that reflect that need and enable the utility to reduce the number of candidates that will be invited to tender or to negotiate.
(3) A utility must take account of the need to ensure adequate competition when selecting the number of candidates.
77.—(1) This regulation applies where there are objective rules and criteria for the exclusion and selection of—
(a)economic operators requesting qualification in a qualification system; or
(b)candidates and tenderers in open, restricted or negotiated procedures, competitive dialogues or innovation partnerships.
(2) Where the objective rules and criteria for the exclusion and selection of those referred to in paragraph (1) include requirements relating to the economic operator’s economic and financial capacity or technical and professional abilities, an economic operator may, where necessary rely upon the capacities of other entities, regardless of the legal nature of the links which it has with them.
(3) With regard to criteria relating to the educational and professional qualifications of the service provider or contractor or those of the undertaking’s managerial staff or to relevant professional experience, economic operators may only rely upon the capacities of other entities where the latter will perform the works or services for which these capacities are required.
(4) Where an economic operator wants to rely upon the capacities of other entities, it must prove to the utility that the necessary resources will be available to it, for example by producing a commitment by those entities to that effect.
(5) For the purposes of paragraph (4), an economic operator requesting qualification in a qualification system must prove that the necessary resources will be available to it throughout the period of the qualification system.
(6) Where, in accordance with regulation 78 (use of exclusion grounds and selection criteria provided for under the Public Contracts (Scotland) Regulations), a utility has referred to exclusion or selection criteria provided for under the Public Contracts (Scotland) Regulations, the utility must verify, in accordance with the provisions applied by regulation 78(4)—
(a)whether the other entities upon whose capacity the economic operator intends to rely fulfil the relevant selection criteria; or
(b)whether there are grounds for exclusion, to which the utility has referred, under regulation 58 of the Public Contracts (Scotland) Regulations.
(7) The utility—
(a)must require the economic operator to replace an entity which does not meet a relevant selection criterion or in respect of which there are compulsory grounds for exclusion; and
(b)may require the economic operator to substitute an entity in respect of which there are non-compulsory grounds for exclusion.
(8) Where an economic operator relies upon the capacities of other entities with regard to criteria relating to economic and financial standing, the utility may require the economic operator and those entities to be jointly liable for the performance of the contract.
(9) A group of economic operators as referred to in regulation 35(4) (economic operators) may rely upon the capacities of participants in the group or of other entities, and paragraphs (1) to (8) apply in relation to such a group in the same way that they apply in relation to an economic operator.
(10) In the case of works contracts, supply contracts requiring siting or installation work and [F1service] contracts, a utility may require certain critical tasks to be performed directly by the tenderer itself or, where the tender is submitted by a group of economic operators as referred to in regulation 35(4) (economic operators), by a participant in that group.
Textual Amendments
F1Word in reg. 77(10) substituted (1.7.2019) by The Public Procurement etc. (Miscellaneous Amendments) (Scotland) Regulations 2019 (S.S.I. 2019/173), regs. 1(2), 2(6)
Commencement Information
78.—(1) This regulation applies to objective rules and criteria for the exclusion and selection of—
(a)economic operators requesting qualification in a qualification system; and
(b)candidates and tenderers in open, restricted or negotiated procedures, competitive dialogues or innovation partnerships.
(2) The objective rules and criteria may include—
(a)the exclusion grounds referred to in regulation 58 of the Public Contracts (Scotland) Regulations on the terms set out in that regulation;
(b)the selection criteria listed in regulation 59 of the Public Contracts (Scotland) Regulations on the terms set out in that regulation, including as regards the limits to requirements concerning yearly turnovers as provided for under regulation 59(9) and (10) of those Regulations.
(3) Where the utility is a contracting authority, the criteria and rules referred to in paragraph (1) must include the exclusion grounds listed in regulation 58(1) to (3) of the Public Contracts (Scotland) Regulations on the terms set out in that regulation.
(4) For the purposes of applying paragraphs (1) to (3), regulations 60 to 62 of the Public Contracts (Scotland) Regulations apply.
(5) For the purposes of paragraphs (2) and (4), any reference to a contracting authority in regulations 58 to 62 of the Public Contracts (Scotland) Regulations must be read as a reference to a utility.
Modifications etc. (not altering text)
C1Reg. 78 modified (18.4.2016) by S.S.I. 2013/50, Sch. 3 para. 10(2)(b) (as substituted by The Utilities Contracts (Scotland) Regulations 2016 (S.S.I. 2016/49), reg. 1, sch. 3 para. 3(2)(b))
Commencement Information
79.—(1) A utility must, where it requires the production of certificates drawn up by independent bodies attesting that the economic operator complies with certain quality assurance standards, including on accessibility for disabled persons, refer to quality assurance systems based on the relevant European standards series certified by accredited bodies.
F2(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(3) A utility must also accept other evidence of equivalent quality assurance measures where the economic operator concerned had no possibility of obtaining such certificates within the relevant time limits for reasons that are not attributable to that economic operator, provided that the economic operator proves that the proposed quality assurance measures comply with the required quality assurance standards.
(4) Where a utility requires the production of certificates drawn up by independent bodies attesting that the economic operator complies with certain environmental management systems or standards, the utility must refer to F3...
F3(a). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F3(b). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(c)F4... environmental management standards based on the relevant European or international standards by accredited bodies,
F5...
(5) Where an economic operator had demonstrably no access to such certificates referred to in paragraph (4) or no possibility of obtaining them within the relevant time limits for reasons that are not attributable to that economic operator, the utility must accept other evidence of environmental management measures, provided that the economic operator proves that these measures are equivalent to those required under the applicable environmental management system or standard.
Textual Amendments
F2Reg. 79(2) omitted (31.12.2020) by virtue of The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(44)(a) (with sch. paras. 1-5)
F3Words in reg. 79(4) omitted (31.12.2020) by virtue of The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(44)(b)(i) (with sch. paras. 1-5)
F4Word in reg. 79(4)(c) omitted (31.12.2020) by virtue of The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(44)(b)(ii) (with sch. paras. 1-5)
F5Words in reg. 79(4) omitted (31.12.2020) by virtue of The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(44)(b)(iii) (with sch. paras. 1-5)
Commencement Information
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: