Ineffectiveness ordersS
104.—(1) Without prejudice to all rights and obligations in respect of the period leading up to the date of the order, an ineffectiveness order made in relation to a contract renders unenforceable all rights and obligations directly arising from the contract in respect of the period commencing on the date of the order.
(2) Subject to any order made under regulation 105(1)(b) (powers of the court) obligations rendered unenforceable by an ineffectiveness order made in relation to a contract must not be performed by the parties to the contract.
(3) Without prejudice to any power of the court to make an ineffectiveness order in relation to a contract based on a framework agreement in accordance with this Part, an ineffectiveness order made in relation to a framework agreement prohibits, with effect from the date of the order, the awarding of contracts based on the framework agreement.
(4) Subject to paragraph (5) and regulation 106 (general interest grounds for not making a declaration of ineffectiveness), the court must make an ineffectiveness order where—
(a)the first ground for ineffectiveness referred to in paragraph (6) applies;
(b)the second ground for ineffectiveness referred to in paragraph (8) applies; or
(c)the third ground for ineffectiveness referred to in paragraph (9) applies.
(5) In proceedings under this Part to which regulation 101(4)(b) (enforcement of duties through the courts) applies, the court does not have power to make an ineffectiveness order if the proceedings would be incompetent if regulation 101(4)(a) applied to the proceedings.
First ground for ineffectiveness
(6) The first ground for ineffectiveness applies where the utility has entered into a contract or has concluded a framework agreement without [F1submitting] a call for competition to the [F2UK e-notification service] in circumstances where the contract or framework agreement was not exempt from the requirement for prior publication of a contract notice.
(7) The first ground for ineffectiveness does not apply where—
(a)the utility [F3submitted to the UK e-notification service a voluntary ex ante transparency notice] expressing its intention to enter into the contract or to conclude the framework agreement and containing—
(i)the name and contact details of the utility;
(ii)a description of the object of the contract or framework agreement;
(iii)a justification of the decision of the utility to award the contract or conclude the framework agreement without prior publication of a contract notice;
(iv)the name and contact details of the economic operator to be awarded the contract or to become party to the framework agreement; and
(v)any other information which the utility considered useful; and
(b)the utility allowed a period of at least 10 days to elapse between the date of publication [F4on the UK e-notification service] of the notice referred to in sub-paragraph (a) and the date on which the utility entered into the contract or concluded the framework agreement.
Second ground for ineffectiveness
(8) The second ground for ineffectiveness applies where all of the following apply—
(a)the utility has breached regulation 98(1) (notices of decisions to award a contract or conclude a framework agreement), 99(1) (standstill period) or 102 (automatic suspension of utility’s power to proceed with contract award);
(b)the utility’s breach referred to in sub-paragraph (a) prevented the economic operator from bringing proceedings or obtaining a remedy before the contract was entered into or the framework agreement was concluded;
(c)in awarding the contract or concluding the framework agreement there has been a breach of the duty owed to the economic operator under these Regulations, other than a breach of regulations 98(1) (notices of decisions to award a contract or conclude a framework agreement), 99(1) (standstill period) or this Chapter;
(d)the utility’s breach referred to in sub-paragraph (c) has affected the chances of the economic operator bringing proceedings under this Part to obtain the contract or become a party to the framework agreement.
Third ground for ineffectiveness
(9) The third ground for ineffectiveness applies where—
(a)the contract is a contract based on a framework agreement or a contract awarded under a dynamic purchasing system;
(b)the contract was awarded in breach of—
(i)regulation 49(5) (framework agreements), in the case of a contract based on a framework agreement (rules governing the award of contracts based on a framework agreement); or
(ii)regulation 50(17) to (19), (21) or (22) (dynamic purchasing systems), in the case of a contract awarded under a dynamic purchasing system (rules governing the award of contracts under a dynamic purchasing system); and
(c)the estimated value of the contract at the relevant time is equal to or greater than the relevant threshold.
(10) The third ground for ineffectiveness does not apply where the utility—
(a)considered the award of the contract to be in accordance with the provisions mentioned in paragraph (9)(b);
(b)has, despite regulation 98(4)(b) (notices of decisions to award a contract or conclude a framework agreement), by notice in writing informed the economic operators that submitted tenders of its decision in relation to the award of the contract and the notice included the information referred to in regulation 98(1) to (3); and
(c)has allowed a period of at least the relevant standstill period to elapse between the date of sending of the notice of its decision to award the contract and the date on which the utility entered into the contract.
Textual Amendments
F1Word in reg. 104(6) substituted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(58)(a)(i) (with sch. paras. 1-5)
F2Words in reg. 104(6) substituted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(58)(a)(ii) (with sch. paras. 1-5)
F3Words in reg. 104(7)(a) substituted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(58)(b)(i) (with sch. paras. 1-5, 9)
F4Words in reg. 104(7)(b) substituted (31.12.2020) by The Public Procurement etc. (EU Exit) (Scotland) (Amendment) Regulations 2020 (S.S.I. 2020/468), regs. 1(2), 6(58)(b)(ii) (with sch. paras. 1-5, 9)
Commencement Information