Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
80.—(1) A utility must base the award of contracts on the most economically advantageous tender assessed from the point of view of the utility.
(2) Where the utility is a person mentioned in regulation 4(1)(a) (utilities) it must not use price only or cost only as the sole award criteria.
(3) A utility must identify the most economically advantageous tender on the basis of the price or cost using a cost-effectiveness approach (such as life-cycle costing in accordance with regulation 81 (life-cycle costing)) and may include the best price-quality ratio which must be assessed on the basis of criteria linked to the subject-matter of the contract in question.
(4) Criteria referred to in paragraph (3) may comprise or include—
(a)quality, including technical merit, aesthetic and functional characteristics, accessibility, design for all users, social, environmental and innovative characteristics and trading and its conditions;
(b)organisation, qualification and experience of staff assigned to performing the contract, where the quality of the staff assigned can have a significant impact on the level of performance of the contract; and
(c)after-sales service and technical assistance, delivery conditions such as delivery date, delivery process and delivery period or period of completion and commitments with regard to parts and security of supply.
(5) The cost element may also take the form of a fixed price or cost on the basis of which economic operators will compete on quality criteria only.
(6) Award criteria must be considered to be linked to the subject-matter of the contract where they relate to the works, supplies or services to be provided under that contract in any respect and at any stage of their life cycle, including factors involved in—
(a)the specific process of production, provision or trading of those works, supplies or services; or
(b)a specific process for another stage of their life cycle,
even where such factors do not form part of their material substance.
(7) Award criteria must—
(a)not have the effect of conferring an unrestricted freedom of choice upon the utility;
(b)ensure the possibility of effective competition; and
(c)be accompanied by specifications that allow the information provided by the tenderers to be effectively verified in order to assess how well the tenders meet the award criteria.
(8) In case of doubt, the utility must verify effectively the accuracy of the information and proof provided by the tenderers.
(9) The utility must specify, in the procurement documents, the relative weighting which it gives to each of the criteria chosen to determine the most economically advantageous tender.
(10) The weightings referred to in paragraph (9) may be expressed by providing for a range with an appropriate maximum spread.
(11) Where weighting is not possible for objective reasons, the utility must indicate the criteria in descending order of importance.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: