Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
10.—(1) This regulation applies where it appears to the Scottish Ministers that—
(a)an application for Electricity Act consent which is before them for determination is an application for Schedule 1 development or an application for Schedule 2 development;
(b)the development to which the application relates has not been the subject of a screening opinion; and
(c)the application is not accompanied by an EIA report.
(2) Where this regulation applies the Scottish Ministers must adopt a screening opinion in respect of the proposed development to which the application for Electricity Act consent relates.
(3) If it appears to the Scottish Ministers that the application for Electricity Act consent is an application for Schedule 2 development but the Scottish Ministers do not consider that the information submitted by the developer in connection with the application for Electricity Act consent includes all the information referred to in regulation 8(2) the Scottish Ministers must seek from the developer such information as they consider remains to be provided by giving notice to the developer describing that information.
11.—(1) This regulation applies where an EIA application which is before the Scottish Ministers for determination is not accompanied by F1... an EIA report.
(2) Where this regulation applies the Scottish Ministers must notify the developer in writing that the submission of an EIA report is required.
(3) Notice under paragraph (2) must be given—
(a)within three weeks beginning with the date on which the application is made; or
(b)where the Scottish Ministers adopt a screening opinion after the date on which the application is made, within seven days beginning with the date of adoption of that screening opinion.
(4) A developer who receives notice under paragraph (2) may within three weeks beginning with the date of the notice write to the Scottish Ministers stating that an EIA report will be provided and may under regulation 12 ask the Scottish Ministers to adopt a scoping opinion.
(5) If the developer does not write in accordance with paragraph (4), the Scottish Ministers are under no duty to deal with the application, and at the end of the three week period the Scottish Ministers must inform the developer in writing that no further action is being taken on the application.
(6) Where the Scottish Ministers have given notice under paragraph (2), they are to determine the application only by refusing Electricity Act consent if the developer does not submit an EIA report
Textual Amendments
F1Words in reg. 11(1) omitted (30.6.2017) by virtue of The Environmental Impact Assessment (Miscellaneous Amendments) (Scotland) Regulations 2017 (S.S.I. 2017/168), regs. 1, 2(4)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: