- Latest available (Revised)
- Point in Time (01/09/2018)
- Original (As made)
Point in time view as at 01/09/2018.
There are currently no known outstanding effects for the The Environmental Authorisations (Scotland) Regulations 2018, Paragraph 20.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
20. SEPA must ensure that a permit or registration for a radioactive substances activity includes such conditions as it considers appropriate to—
(a)prevent the deliberate dilution of radioactive waste for the purpose of being released from regulatory control unless the dilution takes place in normal operations where radioactivity is not a concern or the dilution is a result of mixing radioactive waste with a non-radioactive material for the purposes of re-use or recycling;
(b)ensure adequate protection against any public exposure or contamination liable to extend—
(i)beyond the authorised place; or
(ii)to the ground beneath the authorised place;
(c)ensure that the authorised person—
(i)optimises the level of radiation protection for members of the public;
(ii)uses adequate equipment and procedures for measuring and assessing exposure of members of the public and radioactive contamination of the environment;
(iii)checks that equipment used for measuring and assessing exposure of members of the public and radioactive contamination of the environment is effective and is adequately maintained and calibrated;
(d)ensure that the authorised person seeks appropriate advice from a radiation protection expert in relation to—
(i)the matters set out in sub-paragraph (c); and
(ii)such other matters as SEPA thinks fit,
(e)ensure that the authorised person makes arrangements for keeping control of radioactive material with regard to its location, use and, when it becomes radioactive waste, its management;
(f)ensure, as appropriate and to the extent possible, that the authorised person keeps records of an unsealed source which the authorised person is authorised to hold, including records of location, transfer and disposal or discharge;
(g)ensure that the authorised person keeps records of all sealed sources which the authorised person is authorised to hold, including records of location, transfer and disposal;
(h)ensure that the authorised person informs SEPA promptly of any loss, theft, significant spill, or unauthorised use or release of radioactive material in the form of an unsealed source;
(i)ensure that the authorised person informs SEPA promptly of a transfer of a high-activity sealed source;
(j)ensure that the authorised person informs SEPA promptly of the loss, significant leakage, theft or unauthorised use of a sealed source;
(k)ensure that the authorised person implements a recording and analysis system of significant events involving or potentially involving accidental or unintended public exposure to radioactivity;
(l)ensure that in the event of the public exposure to radioactivity otherwise than in accordance with an authorisation, the authorised person—
(i)informs SEPA without delay;
(ii)carries out a full investigation into the event, and provides SEPA with the results of the investigation, without delay; and
(iii)takes corrective measures to avoid the recurrence of similar events; and
(m)ensure that the authorised person makes adequate arrangements for the security of sealed sources.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: