14. The standard sampling rate and the lower sampling rate may be further reduced as follows—
(a)in the case of the standard sampling rate, the first 8 hectares must be sampled at 1500 ml of soil per hectare, but may be reduced for each additional hectare to a minimum of 400 ml of soil per hectare, or
(b)in the case of the lower sampling rate, the first 4 hectares must be sampled at 400 ml of soil per hectare, but may be further reduced for each additional hectare to a minimum of 200 ml of soil per hectare.
Commencement Information
I1Sch. 2 para. 14 in force at 14.12.2019, see reg. 1(1)