SCHEDULE 2SConditions

PART 5 SReinstatement

31.  A reinstatement plan must be submitted to the Scottish Ministers no later than 6 months before use of the land is to discontinue in terms of article 3(4)(a).S

32.  Reinstatement works must not be commenced until the Scottish Minsters have approved the reinstatement plan.S

Commencement Information

I2Sch. 2 para. 32 in force at 25.3.2021, see art. 1(1)

33.  The reinstatement works must be carried out and completed in accordance with the approved reinstatement plan.S

Commencement Information

I3Sch. 2 para. 33 in force at 25.3.2021, see art. 1(1)

34.  A non-technical summary of the approved reinstatement plan must be published.S

Commencement Information