2024 No. 191

Environmental Protection

The Waste (Materials Facilities) (Scotland) Regulations 2024

Made

Laid before the Scottish Parliament

Coming into force

The Scottish Ministers make the following Regulations in exercise of the powers conferred by sections 18 and 58, and paragraphs 6 and 22 of schedule 2, of the Regulatory Reform (Scotland) Act 20141 and all other powers enabling them to do so.

In accordance with section 19(1) of that Act, the Scottish Ministers have consulted the Scottish Environment Protection Agency and such other persons as they thought fit, including such persons appearing to them to be representative of the interests of local government, industry, agriculture, fisheries or small businesses as they considered appropriate.

Citation and commencement1

These Regulations may be cited as the Waste (Materials Facilities) (Scotland) Regulations 2024 and come into force on 1 April 2025.

Amendment of the Pollution Prevention and Control (Scotland) Regulations 20122

For regulation 32A (schedule 1 conditions: materials recovery facilities) of the Pollution Prevention and Control (Scotland) Regulations 20122, substitute—

Schedule 1 conditions: materials facilities32A

1

SEPA must ensure that a permit granted or varied on or after 1 April 2025 which authorises the operation of a materials facility contains a condition requiring the operator of the installation of which the facility forms part to comply with the Materials Facilities Code.

2

In this regulation—

  • Materials Facilities Code” means the Code of Practice on Sampling and Reporting at Materials Facilities issued by the Scottish Ministers on 24 June 2024,

  • materials facility” means—

    1. a

      a materials recovery facility, being a facility where dry recyclable waste is treated in order to separate that waste into a dry waste stream or streams,

    2. b

      a facility where dry recyclable waste from more than one supplier is consolidated into bulk quantities—

      1. i

        as a first point of consolidation, or

      2. ii

        following the first consolidation of bulk quantities, transferred from other suppliers,

      for the purpose of selling or transferring the dry recyclable waste to other facilities or persons to enable that waste to be prepared for re-use or recycling,

  • dry recyclable waste” means separately collected waste, that is—

    1. a

      glass,

    2. b

      metals,

    3. c

      plastics,

    4. d

      paper,

    5. e

      card (including cardboard),

    6. f

      fibre-based composite material,

  • dry waste stream” means a quantity of dry recyclable waste of the same type (such as glass),

  • fibre-based composite material” means packaging material which is made of paperboard or paper fibres, with a layer of plastic, and which may also have layers of other materials, to form a single unit that cannot be separated by hand,

  • supplier” means—

    1. a

      where dry recyclable waste is collected pursuant to arrangements made under section 45(1)(a) or (b) of the 1990 Act3 by a waste collection authority within the meaning of section 30(3)(c) of that Act4, the waste collection authority, except in a case falling within sub-paragraph (b),

    2. b

      where dry recyclable waste has been transferred from another materials facility, the operator of the materials facility from which that waste was transferred,

    3. c

      in a case not falling within sub-paragraph (a) or (b), the person who collected the dry recyclable waste, or if that person is not known, the person responsible for delivering it to the materials facility.

3

In this regulation, a materials facility does not include a bring site as defined in section 45C(7) of the 1990 Act5.

Amendment of the Waste Management Licensing (Scotland) Regulations 20113

The Waste Management Licensing (Scotland) Regulations 20116 are amended in accordance with regulations 4 to 6.

Amendment of regulation 2 (interpretation)4

In regulation 2 (interpretation)—

a

in paragraph (1)—

i

after the definition for “disposal licence”, insert—

  • dry recyclable waste” means separately collected waste, that is—

    1. a

      glass,

    2. b

      metals,

    3. c

      plastics,

    4. d

      paper,

    5. e

      card (including cardboard),

    6. f

      fibre based composite material,

  • dry waste stream” means a quantity of dry recyclable waste of the same type (such as glass),

ii

after the definition for “exempt activity”, insert—

  • fibre-based composite material” means packaging material which is made of paperboard or paper fibres, with a layer of plastic, and which may also have layers of other materials, to form a single unit that cannot be separated by hand,

iii

after the definition for “local authority”, insert—

  • Materials Facilities Code” means the Code of Practice on Sampling and Reporting at Materials Facilities issued by the Scottish Ministers on 24 June 2024,

iv

after the definition of “special waste”, insert—

  • supplier” means—

    1. a

      where dry recyclable waste is collected pursuant to arrangements made under section 45(1)(a) or (b) of the 1990 Act7 by a waste collection authority within the meaning of section 30(3)(c) of that Act8, the waste collection authority, except in a case falling within sub-paragraph (b),

    2. b

      where dry recyclable waste has been transferred from another materials facility, the operator of the materials facility from which that waste was transferred,

    3. c

      in a case not falling within sub-paragraph (a) or (b), the person who collected the dry recyclable waste, or if that person is not known, the person responsible for delivering it to the materials facility,

b

after paragraph (2), insert—

2A

In these Regulations—

a

materials facility” means—

i

a materials recovery facility, being a facility where dry recyclable waste is treated in order to separate that waste into a dry waste stream or streams, or

ii

a facility where dry recyclable waste from more than one supplier is consolidated into bulk quantities—

aa

as a first point of consolidation, or

bb

following the first consolidation of bulk quantities, transferred from other suppliers,

for the purpose of selling or transferring the dry recyclable waste to other facilities or persons to enable that waste to be prepared for re-use or recycling,

b

a reference to a materials facility does not include a bring site as defined by section 45C(7) of the 1990 Act9.

Amendment of regulation 13B (conditions of waste management licences: materials recovery facilities)5

For regulation 13B (conditions of waste management licences: materials recovery facilities), substitute—

Conditions of waste management licences: materials facilities13B

A waste management licence that is granted or varied on or after 1 April 2025 by the waste regulation authority which authorises the treatment of dry recyclable waste at a materials facility must contain a condition requiring the holder of a licence to comply with the Materials Facilities Code.

New regulation 17A6

After regulation 17 (exemptions from waste management licensing), insert—

Exemptions from waste management licensing: additional requirement for materials facilities17A

A materials facility which carries on an exempt activity set out in paragraph 11 or 17 of schedule 1 must, as a condition of that exemption, comply with the Materials Facilities Code.

GILLIAN MARTINAuthorised to sign by the Scottish MinistersSt Andrew’s House,Edinburgh
EXPLANATORY NOTE

(This note is not part of the Regulations)

These Regulations amend the Pollution Prevention and Control (Scotland) Regulations 2012 (“the 2012 Regulations”) and the Waste Management Licensing (Scotland) Regulations 2011 (“the 2011 Regulations”). The amendments are required following the introduction of the Code of Practice on Sampling and Reporting at Materials Facilities issued by the Scottish Ministers on 24 June 2024 (the “Materials Facilities Code”), replacing the previous Code issued on 2 March 2015, and in order to expand the scope of facilities required to comply with the terms of the Materials Facilities Code.

Regulation 2 substitutes regulation 32A of the 2012 Regulations to require that permits granted or varied for materials facilities on or after 1 April 2025 must include a condition requiring the operator to comply with the Materials Facilities Code.

Regulation 5 substitutes regulation 13B of the 2011 Regulations to require that waste management licences which authorise the treatment of dry recyclable waste at a materials facility granted or varied on or after 1 April 2025 must contain a condition requiring the licence holder to comply with the Materials Facilities Code.

Regulation 6 inserts new regulation 17A into the 2011 Regulations to require that materials facilities carrying on an exempt activity set out paragraph 11 or 17 of schedule 1 of the 2011 Regulations must, as a condition of that exemption, comply with the Materials Facilities Code.

This instrument supports the introduction of Extended Producer Responsibility for packaging. A Business Regulatory Impact Assessment of the effect that Extended Producer Responsibility for packaging will have on the costs of business has been placed in the Scottish Parliament Information Centre. Copies can be obtained from the Scottish Government, Producer Responsibility Division, Area 3H South Victoria Quay, Edinburgh EH6 6QQ, and online at legislation.gov.uk.