17.—(1) Storage in a secure place on any premises of waste of a type listed in the Table in sub-paragraph (2) if—
(a)the waste is stored for the purpose of its recovery;
(b)the total quantity of any particular type of waste stored on those premises at any time does not exceed the corresponding storage limit specified in the Table;
(c)the period for which any particular type of waste is stored on those premises does not exceed the corresponding limits specified in the Table;
(d)in the case of hazardous waste, the waste is stored on an impermeable surface;
(e)in the case of any solvents, chlorofluorocarbons, hydrochlorofluorocarbons, hydrofluorocarbons, paints or edible oil, the waste is stored in sealed leak proof containers; and
(f)each kind of waste listed in the Table and stored on those premises is kept separately.
(2) The Table referred to in sub-paragraph (1) is set out below.
Kind of Wastea | Maximum quantity stored at one time | Maximum duration of storage |
---|---|---|
a Where a description of a waste follows a 6 digit code, only that kind of waste falling within the code is included | ||
02 01 02, 02 02 02 (mammalian protein) | 60,000 tonnes | 12 months |
02 01 02, 02 02 02 (mammalian tallow) | 45,000 tonnes | 12 months |
10 11 12, 15 01 07, 16 01 20, 17 02 02, 19 12 05, 20 01 02 (glass) | 5,000 tonnes | 12 months |
14 06 01* (chlorofluorocarbons, hydrochlorofluorocarbons and hydrofluorocarbons) | 18 tonnes | 6 months |
14 06 02*, 14 06 03*, 20 01 13* (solvents and solvent mixtures) | 5 cubic metres | 6 months |
15 01 01, 19 12 01, 20 01 01 (paper and cardboard) | 15,000 tonnes | 12 months |
15 01 01, 19 12 01, 20 01 01 (cartons) | 500 tonnes | 12 months |
15 01 02, 20 01 39 (plastic) | 500 tonnes | 12 months |
15 01 04, 20 01 40 (cans and foil) | 500 tonnes | 12 months |
16 01 03 (tyres) | 1,000 tyres | 12 months |
17 01 01 to 17 08 02 except for 17 03 02, 17 05 04, 17 05 06 and 17 05 08 (non-hazardous construction and demolition waste articles which are to be used for construction work and are capable of being used in their existing state) | 100 tonnes | 12 months |
15 01 03, 17 02 01, 17 02 04*, 20 01 37*, 20 01 38 (wood including telegraph poles and railway sleepers) | 100 tonnes | 12 months |
15 01 09, 19 12 08, 20 01 10, 20 01 11 (textiles and clothes) | 1,000 tonnes | 12 months |
20 01 25 (edible oil) | 500 tonnes | 12 months |
20 01 27*, 20 01 28 (paints (excluding specialist and industrial paints, wood preservatives, aerosol and spray paints, inks, adhesives and resins) pending re-use as paint) | 10,000 litres | 6 months |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: