16.—(1) This paragraph provides for the calculation of a period referred to in paragraph 15(2).
(2) The period starts—
(a)on the day the regulator receives a duly-made application; or
(b)if paragraph 10 applies, on the day the appropriate authority complies with paragraph 10(3).
(3) In calculating the period the following periods must be ignored—
(a)a period from the service of a notice requiring further information under paragraph 4(1) to the receipt by the regulator of that information;
(b)a period for representations mentioned in paragraph 9(3)(c) to the extent that it does not overlap with a period for representations mentioned in paragraph 6(1)(c);
(c)a period during which national security or confidentiality is being considered in relation to the application, that is to say—
(i)any period during which a determination under regulation 47(3), 47(7) or 50 is being considered (including any appeal), or
(ii)a period of 15 working days after the service of a notice under regulation 49(1); and
(d)if the regulator informs the public in relation to a draft decision in accordance with paragraph 1(d) of Annex V to the IPPC Directive, a period of 20 working days.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: