15.—(1) In each scheme year a compulsory scheme electricity supplier must, subject to paragraph (2), incur spending under this Part to the amount of its non-core spending obligation.
(2) In relation to scheme year 1, 2 or 3, a compulsory scheme electricity supplier is not in breach of paragraph (1) if the amount of spending incurred by the supplier under this Part (as determined by the Authority in accordance with regulation 29(d)) is equal to or greater than 99% of its non-core spending obligation.
(3) The spending to be incurred by a compulsory scheme electricity supplier under this Part—
(a)must, in each scheme year, include the provision of rebates to broader group customers under Chapter 2;
(b)if the supplier is a relevant supplier, may in scheme years 1, 2 and 3 include legacy spending under Chapter 3, subject to the limits in paragraph (4)(a) and (c); and
(c)may include spending on industry initiatives under Chapter 4, subject to the limits in paragraph (4)(b) and (c).
(4) The maximum amount of spending that a compulsory scheme electricity supplier may count towards its non-core spending obligation—
(a)under Chapter 3, is the relevant percentage of—
(i)£140 million in scheme year 1;
(ii)£70 million in scheme year 2; and
(iii)£35 million in scheme year 3;
(b)under Chapter 4, in any scheme year, is the relevant percentage of £30 million; and
(c)under Chapters 3 and 4 combined, is the relevant percentage of—
(i)£150 million in scheme year 1;
(ii)£85 million in scheme year 2; and
(iii)£53 million in scheme year 3.
(5) In paragraph (4), “the relevant percentage” means the percentage determined under regulation 13(2).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: