PART 2Eligibility and matters relating to eligibility
CHAPTER 2Eligibility criteria for technologies
Other eligibility requirements for technologies12
1
The requirements referred to in regulation 4(b) are—
a
installation of the plant was completed and the plant was first commissioned on or after 15th July 2009;
b
the plant was new at the time of installation;
c
the plant uses liquid or steam as a medium for delivering heat to the space, water or process;
d
heat generated by the plant is used for an eligible purpose.
2
The requirements of paragraph (1)(a) and (b) are deemed to be satisfied where the plant was previously generating electricity only, using solid biomass or biogas, and was first commissioned as a CHP system on or after 15th July 2009.
3
But the requirements of paragraph (1)(a) and (b) are not satisfied where the plant was previously generating heat only and was first commissioned as a CHP system on or after 15th July 2009.