4.—(1) For the purposes of regulation 3(3), the relevant amount is—
(a)where sub-paragraph (b) does not apply, the amount of electricity which is the subject of the application under regulation 3(1) which meets the criteria in regulation 3(3)(a) to (c); or
(b)where this paragraph applies the amount given by—
where—
“APF” is the amount of electricity which is the subject of the application under regulation 3(1) which meets the criteria in regulation 3(3)(a) to (c);
“TGE” is the total amount of electricity supplied by all suppliers which meets the following criteria—
“CAP” is the amount of the cap which applies in respect of green excluded electricity supplied during that quarterly obligation period.
(2) Paragraph (1)(b) applies where the CFD counterparty determines that TGE exceeds the amount of the cap for the quarterly obligation period in which that electricity was supplied.
(3) For the purposes of this regulation, the cap which applies in respect of green excluded electricity supplied during a quarterly obligation period is—
(a)for each quarterly obligation period in financial year 2015, 1,844,830 MWh;
(b)for each quarterly obligation period in a subsequent financial year, the amount of the cap which applied in the last quarterly obligation period of the previous financial year multiplied by 1.1.
(4) Where the CFD counterparty has determined that an amount of electricity is green excluded electricity but subsequently determines that paragraph (1)(b) applies, or that the relevant amount calculated under paragraph (1)(b) is different to that previously determined, only the relevant amount of electricity as most recently determined constitutes green excluded electricity for the purpose of any subsequent calculation of CFD period contributions under the ESO Regulations.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: