The Electricity Capacity (Amendment) Regulations 2016

New regulation 29A

This section has no associated Explanatory Memorandum

38.  After regulation 29 insert—

Second DSR transitional auction

29A.(1) This regulation applies to the DSR transitional auction held in the auction window commencing on 1st September 2016.

(2) In this auction—

(a)regulation 15(4) applies as if the minimum capacity threshold is 500 kilowatts; and

(b)regulation 29(1) applies as if for sub-paragraphs (a) and (b) there were substituted “a demand side response CMU which does not provide DSR capacity by using a generating unit..