- Draft legislation
This is a draft item of legislation. This draft has since been made as a UK Statutory Instrument: The Greenhouse Gas Emissions Trading Scheme Order 2020 No. 1265
46.—(1) This article applies for the purpose of determining the price (the “carbon price”) per tonne of carbon dioxide equivalent for a scheme year.
(2) The carbon price for the 2021 scheme year is the sum of the relevant amount for each auction of allowances held in the period beginning on 1st January 2021 and ending on 11th November 2021 under regulations made by the Treasury under the Finance Act 2020 divided by the sum of the allowances sold at all those auctions.
(3) In paragraph (2), the relevant amount for an auction is the auction clearing price (that is to say, the price per allowance that, in accordance with the auction rules, each successful bidder must pay, irrespective of the original bid) multiplied by the number of allowances sold at the auction.
(4) The carbon price for the 2022 scheme year or any subsequent scheme year (the “relevant scheme year”) is the average end of day settlement price, calculated over the relevant period, of the December futures contract for the relevant scheme year, as traded on the relevant carbon market exchange.
(5) For the purposes of paragraph (4), the “average” end of day settlement price is calculated by dividing the sum of the end of day settlement price for each day in the relevant period for which an end of day settlement price is published by the number of days in the relevant period for which an end of day settlement price is published.
(6) In paragraphs (4) and (5)—
“end of day settlement price”, in relation to a futures contract, means the end of day settlement price per tonne of carbon dioxide equivalent published by the carbon market exchange on which the futures contract is traded;
“futures contract” means a futures contract for allowances;
“relevant carbon market exchange”, in relation to a relevant scheme year, means the largest carbon market exchange as determined by volume of sales in the relevant period of the December futures contract for the relevant scheme year traded on the exchange;
“relevant period” means—
in relation to the carbon price for the 2022 scheme year, the period beginning on 1st January 2021 and ending on 11th November 2021;
in relation to the carbon price for the 2023 scheme year and any subsequent scheme year, the 12-month period ending on 11th November in the year preceding the relevant scheme year.
(7) The UK ETS authority must publish the carbon price for the 2021 scheme year on or before 30th November 2021.
(8) The UK ETS authority must publish the carbon price for subsequent scheme years on or before 30th November in the year preceding the scheme year.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include: