3.—(1) Every electricity supplier who supplies electricity during a quarterly obligation period must, subject to paragraph (3), pay an RCC period contribution to the revenue collection counterparty in respect of that period.
(2) That contribution is to be calculated in accordance with regulation 4.
(3) Where the amount of a supplier’s RCC period contribution in respect of a quarterly obligation period is a negative number—
(a)the amount the supplier must pay under paragraph (1) in respect of that period is zero; and
(b)the revenue collection counterparty must pay the absolute value of that amount to that supplier.
(4) For the purpose of ensuring that the RCC period contribution is paid—
(a)an electricity supplier must make—
(i)interim rate payments in accordance with regulation 7(1),
(ii)supplier data reconciliation payments in accordance with regulation 8(2),
(iii)reserve payments in accordance with regulation 10(1),
(iv)any additional reserve payments required by regulation 13(3), and
(v)any reconciliation payments required by regulation 16(3)(a); and
(b)the revenue collection counterparty must make—
(i)counterparty data reconciliation payments in accordance with regulation 8(3), and
(ii)any required reconciliation payments in accordance with regulation 16(3)(b).
4.—(1) The RCC period contribution for a supplier for a quarterly obligation period is the amount given by—
where—
GP is the total amount of revenue collection counterparty payments which the revenue collection counterparty was required to make in the quarterly obligation period;
SoS repayment is—
unless sub-paragraph (b) or (c) applies, the SoS payment in respect of the quarterly obligation period that ended three whole quarterly obligation periods before the quarterly obligation period for which this calculation is made (a “full SoS repayment”);
unless paragraph (c) applies and if the Secretary of State has specified that only a proportion of the full SoS repayment is to be used for the purposes of this paragraph, that amount;
where the contribution is for any of first four quarterly obligation periods, zero;
CP is the total amount of RCC party payments which the revenue collection counterparty received from RCC parties in the quarterly obligation period;
SoS payment is the total amount of any SoS funds that the Secretary of State has specified are to be used when calculating the RCC period contribution in respect of the quarterly obligation period;
DI is any amount of interest which was paid by virtue of regulation 7(6), 8(7), 10(2), 13(7), 16(5) or 17(7) during that period, less any amount of that interest which was paid to electricity suppliers by virtue of regulation 18(2);
SQS is the amount of electricity supplied by that supplier in the quarterly obligation period;
XEP is the amount of EII excluded electricity supplied by that supplier in the quarterly obligation period;
TQS is the total amount of electricity supplied by all suppliers in the quarterly obligation period; and
AXP is the total amount of EII excluded electricity supplied by all suppliers in the quarterly obligation period.
(2) For the purposes of this regulation, the amount of electricity supplied by a supplier in a quarterly obligation period is the amount of electricity which the BSCCo determines was supplied by that supplier on the basis of—
(a)Final Reconciliation Volume Allocation Runs for each day within the quarterly obligation period; or
(b)where a Post-Final Volume Allocation Run has occurred in relation to a day on which electricity was supplied, the Post-Final Volume Allocation Run for that day.
(3) Where the revenue collection counterparty makes a determination under these Regulations which requires the determination of the amount of electricity supplied on a day which is EII excluded electricity, it must, where possible, base that determination of EII excluded electricity on information derived from the most recent BSC volume allocation run carried out by the BSCCo in relation to the day on which the electricity was supplied.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: