PART 1Introduction
Citation, commencement and extent1.
(1)
This Order may be cited as the Electricity and Gas (Energy Company Obligation) Order 2023.
(2)
Parts 1 to 9 come into force on the day after the day on which this Order is made.
(3)
Part 10 comes into force on the 21st day after the day on which this Order is made.
(4)
This Order extends to England and Wales and Scotland.
Interpretation2.
(1)
(2)
In Parts 1 to 9—
“annual cost savings”, in relation to a measure, means—
(a)
the money that would be saved by the measure annually in heating domestic premises to 21 degrees Celsius in the main living areas and 18 degrees Celsius in all other areas; and
(b)
where the measure also results in savings in the cost of heating water, the money that would be saved by the measure annually in heating water in the premises;
“cavity wall insulation” means insulation between the leaves of a cavity wall;
“commencement date” means the date on which Parts 1 to 9 come into force;
“completed”, in relation to a measure, has the meaning given in paragraph (4);
“ECO4A phase” means one of the three phases as follows—
(a)
the period beginning with the commencement date and ending with 31st March 2024 (“phase A”);
(b)
the twelve months ending with 31st March 2025 (“phase B”);
(c)
the twelve months ending with 31st March 2026 (“phase C”);
“ECO4A qualifying action” has the meaning given in article 10;
“equivalent ECO4 phase” means—
(a)
in relation to phase A, phase 2;
(b)
in relation to phase B, phase 3;
(c)
in relation to phase C, phase 4,
and for the purposes of this definition, “phase 2”, “phase 3” and “phase 4” have the meanings given in article 2(1) of the 2022 Order;
“flat in-fill measure” means a measure that meets the condition in article 20 (see paragraph (1) of that article);
“group” means a group of companies that includes as members of the group at least two companies that are licence-holders, and for the purpose of this definition—
(a)
“company” includes any body corporate; and
(b)
“heating control measure” means—
(a)
a thermostat that is connected to a system which provides heat for the purposes of space heating; or
(b)
a type of control listed in sections 9.4.1 to 9.4.6 of the Standard Assessment Procedure;
“house in-fill measure” means a measure that meets the condition in article 21 (see paragraph (1) of that article);
“in-fill measure” means a flat in-fill measure or a house in-fill measure;
“insulation measure” means a measure which—
(a)
improves the insulating properties of domestic premises;
(b)
in the case of a measure installed at domestic premises other than a mobile home, is one of the following—
- (i)
cavity wall insulation;
- (ii)
solid wall insulation;
- (iii)
internal or external insulation of a wall, but not including cavity wall insulation or solid wall insulation;
- (iv)
loft insulation;
- (v)
insulation of the walls and ceiling of a habitable room in the roof space of the domestic premises;
- (vi)
insulation of a flat roof;
- (vii)
insulation of a pitched roof;
- (viii)
insulation against the escape of heat from a habitable room into the ground, or space, beneath the domestic premises; and
(c)
in the case of a measure installed at a mobile home, is the insulation of the floor, walls and ceiling of the mobile home;
“landlord” has the meaning given in regulation 21(b)(i) of the 2015 Regulations;
“licence-holder” means a person holding one or both of the following—
(a)
(b)
“loft insulation” means insulation against the escape of heat from a habitable room into the loft area of a domestic premises;
“pre-installation energy efficiency assessment” means an RdSAP assessment performed in accordance with article 22(1)(a)(i);
“pre-installation SAP band” means the SAP band which is determined for a domestic premises pursuant to a pre-installation energy efficiency assessment;
“PRS Exemptions Register” has the meaning given in regulation 36 of the 2015 Regulations;
“qualification year” means—
(a)
for phase A, the year 2022;
(b)
for phase B, the year 2023;
(c)
for phase C, the year 2024;
“RdSAP assessment” means an assessment of the energy efficiency of domestic premises using the Reduced Data Standard Assessment Procedure;
“SAP band” means the band running from A to G which is assigned to a SAP rating under the Reduced Data Standard Assessment Procedure;
“SAP rating” means the energy efficiency rating of a domestic premises determined in accordance with the Reduced Data Standard Assessment Procedure;
“score” means the contribution made by an ECO4A qualifying action towards a participant’s total home-heating cost reduction obligation;
“statement of intent”, in relation to a relevant authority, means a statement that the relevant authority intends to identify households living in domestic premises that may benefit from the installation of an ECO4A eligible measure, and for the purposes of this definition, an “ECO4A eligible measure” is a measure that would be capable of satisfying article 10 if installed at the domestic premises;
“total low-income minimum requirement” means, in relation to a participant, the sum of the participant’s low-income minimum requirements, if any, for each ECO4A phase.
(3)
In Parts 1 to 9, the following expressions have the same meanings as in the 2022 Order—
“domestic premises”;
“mobile home”;
“owner-occupied premises”;
“private domestic premises”;
“private rented premises”;
“qualifying supply”;
“relevant authority”;
“social housing”;
“solid wall insulation”;
(4)
For the purposes of Parts 1 to 9—
(a)
(b)
a measure is completed when the installation of the measure is completed.