30.—(1) This regulation sets out other information which must be included in a contract award notice published by a private utility under section 50(1) of the PA 2023 where the contract is being awarded in accordance with a framework.
(2) The information is—
(a)the same information referred to in regulation 27(2)(a) to (r), except sub-paragraphs (c)(iv), (i), (j), (n), (o) and (p),
(b)the estimated date when the contract will be entered into,
(c)a description of any option in the public contract—
(i)to supply additional goods, services or works, or
(ii)to extend or renew the term of the contract,
(d)where the framework is arranged by reference to lots, the distinct number given by the contracting authority to the lot under which the contract is being awarded,
(e)details of which of the following procedures was used to award the public contract—
(i)a competitive selection process for frameworks under section 46 of the PA 2023, or
(ii)an award without further competition under section 45(4) of the PA 2023, and
(f)if sub-paragraph (e)(ii) applies, an explanation of why the contracting authority considered that it applies by reference to section 45(4) of the PA 2023.
(3) Nothing in this regulation prevents a contracting authority from publishing other information that relates to the same procurement in the notice.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: