- Latest available (Revised)
- Original (As enacted)
This is the original version (as it was originally enacted). This item of legislation is currently only available in its original format.
(1)If any requirements of the protected authority under the relevant enactment conflict with any requirements of the Secretary of State under section 13 (Tidal works not to be executed without approval of Secretary of State) of this Act the latter shall prevail.
(2)In any case where any plans have been submitted to both protected authorities and either or both those authorities disapprove such plans the plans shall not be deemed to have been approved unless approved by both the authorities and in any arbitration proceedings which may take place as a result of the disapproval of one of the authorities the protected authority which is not a party to those proceedings shall be entitled to be heard in such proceedings and the plans as settled by such arbitration shall be deemed to have been approved by such protected authority (whether or not it has been heard in the proceedings).
(3)In this section—
“the protected authority” means A.B. Ports or the rivers authority;
“the relevant enactment” means, in relation to A.B. Ports, section 26 (For protection of A.B. Ports) of this Act and, in relation to the rivers authority, section 27 (For protection of rivers authority) of this Act.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: