SCHEDULES

[F1SCHEDULE 3E+W+S PROCEDURE FOR MAKING HARBOUR REVISION AND EMPOWERMENT ORDERS

Textual Amendments

Modifications etc. (not altering text)

C1Sch. 3 modified (1.4.2001) by 2000 c. 38, s. 37, Sch. 5 para. 1(2)(j) (with s. 106); S.I. 2001/869, art.2

C2Sch. 3: transfer of functions (1.4.2018) by Wales Act 2017 (c. 4), ss. 29(2)(b)(ii), 71(4) (with Sch. 7 paras. 1, 6, 9); S.I. 2017/1179, reg. 3(g) (with transitional provisions and savings in S.I. 2018/278, reg. 2, Sch.)

PART IE+W+S ORDERS MADE ON APPLICATION TO THE SECRETARY OF STATE

[F2Deferral of environmental impact assessment: direction and effect of directionE+W+S

20F.(1)The Secretary of State may make an order authorising a deferred project only if satisfied that—E+W+S

(a)the conclusion mentioned in paragraph 20E(3)(a) is up to date, and

(b)making the order in the form of the draft submitted with the application, or with modifications, would be compatible with the decision made by the consenting authority following the assessment mentioned in paragraph 20D(1)(b).

(2)A conclusion is to be taken to be up to date for the purposes of sub-paragraph (1)(a) if, in the opinion of the Secretary of State, it addresses the likely significant effects of the project on the environment.

(3)The Secretary State must consult the consenting authority if satisfied that it is appropriate to do so for the purposes of sub-paragraph (1)(b).]]