C1C2C3C4C5C6C7C8C9C10C11C12C13C14C15C16C17C18C19C20C21C22C23C24C25C26C27C28C29C30C31C32C33C34C35C36C38C37C39C40C41C42C43C44C45C46C47C48C50C49C51C52C53C54C55C56F1SCHEDULE 2ACounter-notice requiring purchase of land not in notice to treat

Annotations:
Amendments (Textual)
Modifications etc. (not altering text)
C17

Sch. 2A excluded (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 25(3)(a) (with arts. 7, 25(4))

PART 2Counter-notice where authority has taken possession

Acquiring authority must respond to counter-notice within 3 months

20

The authority must serve notice of their decision on the owner within the period of 3 months beginning with the day on which the counter-notice is served (“the decision period”).