SCHEDULES

C1C2C3C4C5C6C7C8C9C10C11C12C13C14C15C16C17C18C19C20C21C22C23C24C25C26C27C28C29C30C31C32C33C34C35F1SCHEDULE 2ACounter-notice requiring purchase of land not in notice to treat

Annotations:
Amendments (Textual)
Modifications etc. (not altering text)
C17

Sch. 2A excluded (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 25(3)(a) (with arts. 7, 25(4))

PART 3Determination by the Upper Tribunal

Role of the Upper Tribunal

27

If the Upper Tribunal determines that the severance of the land proposed to be acquired would have either of the consequences described in paragraph 26(1) it must determine how much of the additional land the acquiring authority ought to be required to take in addition to the land proposed to be acquired.