Compulsory Purchase Act 1965

7 Measure of compensation in case of severance. E+W

In assessing the compensation to be paid by the acquiring authority under this Act regard shall be had not only to the value of the land to be purchased by the acquiring authority, but also to the damage, if any, to be sustained by the owner of the land by reason of the severing of the land purchased from the other land of the owner, or otherwise injuriously affecting that other land by the exercise of the powers conferred by this or the special Act.

Modifications etc. (not altering text)

C2Pt. 1 applied (with modifications) (13.3.2024) by The Medworth Energy from Waste Combined Heat and Power Facility Order 2024 (S.I. 2024/230), arts. 1, 30 (with art. 24, Sch. 11 paras. 5, 22, 37, 47, 82, 110)

C3Pt. 1 applied (with modifications) (28.3.2024) by The A66 Northern Trans-Pennine Development Consent Order 2024 (S.I. 2024/360), art. 1, Sch. 5 paras. 4, 5 (with arts. 18, 35, Sch. 9)

C7Pt. 1 applied (with modifications) (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 31 (with arts. 5, 27, 53, Sch. 8 paras. 6, 64)

C11S. 7 applied (with modifications) (31.3.1994) by 1994 c. iv, s. 17, Sch. 2 para. 1

S. 7 applied (18.12.1996) by 1996 c. 61, s. 51(6)

S. 7 applied (with modifications) (1.10.1998) by 1975 c. 70, Sch. 4 Pt. 1II para. 6(4)(a) (as inserted (1.10.1998) by 1998 c. 38, s. 127, Sch. 13 para. 3 (with ss. 139(2), 143(2)); S.I. 1998/2244, art. 4)

C17S. 7 modified by 1981 c. 66, Sch. A1 para. 16(4) (as inserted (19.7.2017) by Neighbourhood Planning Act 2017 (c. 20), ss. 41, 46(1); S.I. 2017/767, reg. 2(j))

C19S. 7 applied (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 27(4) (with art. 7)