Changes over time for: Cross Heading: Certificate of lawful use or development

 Help about opening options

Version Superseded: 10/08/1992

Status:

Point in time view as at 01/02/1991. This version of this cross heading contains provisions that are not valid for this point in time. Help about Status

Close

Status

Not valid for this point in time generally means that a provision was not in force for the point in time you have selected to view it on.

Changes to legislation:

There are currently no known outstanding effects for the Town and Country Planning (Scotland) Act 1972 (repealed 27.5.1997), Cross Heading: Certificate of lawful use or development. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

[F1 Certificate of lawful use or development]S

Textual Amendments

F1Ss. 90-90C and cross heading substituted for s. 90 ((10.8.1992 for certain purposes under s. 90B, otherwise 25.9.1992)) by Planning and Compensation Act 1991 (c. 34, SIF 123:2), s. 42(1) (with s. 84(5)); S.I. 1992/1937, arts.3, 4 (with art. 5).

90 Certification of established use.S

(1)For the purposes of this Part of this Act, a use of land is established if—

(a)it was begun before the beginning of 1965 without planning permission in that behalf and has continued since the end of 1964; or

(b)it was begun before the beginning of 1965 under a planning permission in that behalf granted subject to conditions or limitations, which either have never been complied with or have not been complied with since the end of 1964; or

(c)it was begun after the end of 1964 as the result of a change of use not requiring planning permission and there has been, since the end of 1964, no change of use requiring planning permission.

(2)Where a person having an interest in land claims that a particular use of it has become established, he may apply to the. . . F2 planning authority for a certificate (in this Act referred to as an “established use certificate”) to that effect:

Provided that no such application may be made in respect of the use of land as a single dwellinghouse, or of any use not subsisting at the time of the application.

(3)An established use certificate may be granted (either by the. . . F2 planning authority or, under section 91 of this Act, by the Secretary of State)—

(a)either for the whole of the land specified in the application, or for a part of it;

(b)in the case of an application specifying two or more uses, either for all those uses or for some one or more of them.

(4)On an application to them under this section, the. . . F2 planning authority shall, if and so far as they are satisfied that the applicant’s claim is made out, grant to him an established use certificate accordingly; and if and so far as they are not so satisfied, they shall refuse the application.

(5)Where an application is made to a. . . F2 planning authority for an established use certificate, then unless within such period as may be prescribed by a development order, or within such extended period as may at any time be agreed upon in writing between the applicant and the. . . F2 planning authority, the authority give notice to the applicant of their decision on the application, then, for the purposes of section 91(2) of this Act, the application shall be deemed to be refused.

(6)Schedule 12 to this Act shall have effect with respect to established use certificates and applications therefor and to appeals under section 91 of this Act.

(7)An established use certificate shall, as respects any matters state therein, be conclusive for the purposes of an appeal to the Secretary of State against an enforcement notice served in respect of any land to which the certificate relates, but only where the notice is served after the date of the application on which the certificate was granted.

(8)If any person, for the purpose of procuring a particular decision on an application (whether by himself or another) for an established use certificate or on an appeal arising out of such an application—

(a)knowingly or recklessly makes a statement which is false in a material particular; or

(b)with intent to deceive, produces, furnishes, sends or otherwise makes use of any document which is false in a material particular; or

(c)with intent to deceive, withholds any material information,

he shall be guilty of an offence and liable on summary conviction to a fine not exceeding £400 or, on conviction on indictment, to imprisonment for a term not exceeding two years or a fine, or both.

Textual Amendments

Valid from 10/08/1992

[F3F390ACertificate of lawfulness of proposed use or development.S

(1)If any person wishes to ascertain whether—

(a)any proposed use of buildings or other land; or

(b)any operations proposed to be carried out in, on, over or under land,

would be lawful, he may make an application for the purpose to the planning authority specifying the land and describing the use or operations in question.

(2)If, on an application under this section, the planning authority are provided with information satisfying them that the use or operations described in the application would be lawful if instituted or begun at the time of the application they shall issue a certificate to that effect; and in any other case they shall refuse the application.

(3)A certificate under this section shall—

(a)specify the land to which it relates;

(b)describe the use or operations in question (in the case of any use falling within one of the classes specified in an order under section 19(2)(f) of this Act, identifying it by reference to that class);

(c)give the reasons for determining the use or operations to be lawful; and

(d)specify the date of the application for the certificate.

(4)There shall be an irrefutable presumption as to the lawfulness of any use or operations for which a certificate is in force under this section unless there is a material change, before the use is instituted or the operations are begun, in any of the matters relevant to determining such lawfulness.]

Textual Amendments

F3Ss. 90-90C and cross heading substituted for s. 90 (10.8.1992 for certain purposes under s. 90B, otherwise 25.9.1992) by Planning and Compensation Act 1991 (c. 34, SIF 123:2), s. 42(1) (with s. 84(5)); S.I. 1992/1937, arts. 3, 4 (with art. 5).

Valid from 10/08/1992

[F4F490BCertificates under sections 90 and 90A: supplementary provisions.S

(1)An application for a certificate under section 90 or 90A of this Act shall be made in such manner as may be prescribed by regulations under this Act or a development order and shall include such particulars, and be verified by such evidence, as may be required by such regulations or such an order or by any directions given under such regulations or such an order or by the planning authority.

(2)Provision may be made by such regulations or a development order for regulating the manner in which applications for certificates under those sections are to be dealt with by planning authorities.

(3)In particular, such regulations or such an order may provide for requiring the authority—

(a)to give to any applicant within such time as may be prescribed by the regulations or the order such notice as may be so prescribed as to the manner in which his application has been dealt with; and

(b)to give to the Secretary of State and to such other persons as may be prescribed by or under the regulations or the order, such information as may be so prescribed with respect to such applications made to the authority, including information as to the manner in which any application has been dealt with.

(4)A certificate under either of those sections may be issued—

(a)for the whole or part of the land specified in the application; and

(b)where the application specifies two or more uses, operations or other things, for all of them or some one or more of them,

and shall be in such form as may be prescribed by such regulations or a development order.

(5)A certificate under section 90 or 90A shall not affect any matter constituting a failure to comply with any condition or limitation subject to which planning permission has been granted unless that matter is described in the certificate.

(6)In section 31 of this Act references to applications for planning permission shall include references to applications for certificates under section 90 or 90A of this Act.

(7)A planning authority may revoke a certificate under either of those sections if, on the application for the certificate—

(a)a statement was made or document used which was false in a material particular; or

(b)any material information was withheld.

(8)Provision may be made by such regulations or a development order for regulating the manner in which certificates may be revoked and the notice to be given of such revocation.]

Textual Amendments

F4Ss. 90-90C and cross heading substituted for s. 90 (10.8.1992 for certain purposes under s. 90B, otherwise 25.9.1992) by Planning and Compensation Act 1991 (c. 34, SIF 123:2), s. 42(1) (with s. 84(5)); S.I. 1992/1937, arts. 3, 4 (with art. 5).

Valid from 10/08/1992

[F5F590COffences.S

(1)If any person, for the purpose of procuring a particular decision on an application (whether by himself or another) for the issue of a certificate under section 90 or 90A of this Act—

(a)knowingly or recklessly makes a statement which is false or misleading in a material particular;

(b)with intent to deceive, uses any document which is false or misleading in a material particular; or

(c)with intent to deceive, withholds any material information,

he shall be guilty of an offence.

(2)A person guilty of an offence under subsection (1) of this section shall be liable—

(a)on summary conviction, to a fine not exceeding the statutory maximum; or

(b)on conviction on indictment, to imprisonment for a term not exceeding two years, or a fine, or both.]

Textual Amendments

F5Ss. 90-90C and cross heading substituted for s. 90 (10.8.1992 for certain purposes under s. 90B, otherwise 25.9.1992) by Planning and Compensation Act 1991 (c. 34, SIF 123:2), s. 42(1) (with s. 84(5)); S.I. 1992/1937, arts.3, 4 (with art. 5).

91 Grant of certificate by Secretary of State on referred application or appeal against refusal.S

(1). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . F6

(2)Where an application is made to a. . . F7 planning authority for an estblished use certificateand is refused, or is refused in part, the applicant may by notice under this subsection appeal to the Secretary of State; and on any such appeal the Secretary of State shall—

(a)if and so far as he is satisfied that the authority’s refusal is not well-founded, grant to the appellant an established use certificate accordingly or, as the case may be, modify the certificate granted by the authority on the application; and

(b)if and so far as he is satisfied that the authority’s refusal is well-founded, dismiss the appeal.

(3)On. . . F8 an appeal to him under subsection (2) of this section, the Secretary of State may, in respect of any use of land for which an established use certificate is not granted (either by him or by the. . . F7 planning authority), grant planning permission for that use or, as the case may be, for the continuance of that use without complying with some condition subject to which a previous planning permission was granted.

(4)Before determining an. . . F8 appeal under this section the Secretary of State shall, if either the. . . F8 appellant. . . F8 or the. . . F7 planning authority so desire, afford to each of them an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for the purpose.

(5)In the case of any use of land for which the Secretary of State has power to grant planning permission under this section, the. . . F8 appellant shall be deemed to have made an application for such planning permission; and any planning permission so granted shall be treated as granted on the said application.

(6)Subject to section 279 of this Act, Schedule 7 to this Act applies to appeals under this section.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources