SCHEDULES

SCHEDULE 22S Transitional Provisions and Savings

Part XVIS Miscellaneous and Supplementary

Development authorised under enactments repealed by Act of 1947S

76(1)Where any works on land existing at the appointed day, or any use to which land was put on that day, had been authorised by a permission granted subject to conditions under a scheme under the M1Town and Country Planning (Scotland) Act 1932 (or under an enactment repealed by that Act) or under an order made under section 10(1) of that Act (in the subsequent provisions of this Schedule referred to as “a planning scheme” and “an interim development order”) the provisions of Parts III and V of this Act, the provisions of Part IX of this Act relating to purchase notices, and the provisions of sections 214 to 217 of this Act, shall apply in relation to those works or that use as if the conditions had been imposed on the grant of planning permission.

(2)Without prejudice to the generality of sub-paragraph (1) of this paragraph, where any such permission was granted subject to conditions (in whatever form) restricting the period for which the works or use might be continued on the land, then, if that period had not expired at the appointed day and the works were or are not removed, or the use discontinued, at the end of that period, the provisions of Part V of this Act relating to enforcement notices shall apply in relation thereto as if the works had been carried out, or the use begun, as the case may be, at the end of that period and without the grant of planning permission in that behalf.

(3)The power of a F1 planning authority under Part III of this Act to grant permission for the retention on land of buildings or works constructed or carried out before the date of the application, or the continuance of any use of land instituted before that date, shall include power to grant such permission in respect of any works or use authorised by a permission granted subject to any such conditions as are mentioned in sub-paragraph (2) of this paragraph.

(4)Where at any time before the appointed day it was determined under the M2Building Restrictions (War-Time Contraventions) Act 1946 that any works on land or any use of land should be deemed to comply with planning control (within the meaning of that Act) subject to any conditions specified in the determination, the provisions of this paragraph shall apply in relation to those works or that use as if those conditions had been imposed on the grant of permission under a planning scheme or an interim development order.

(5)Provisions may be made by regulations under this Act for applying the preceding provisions of this paragraph, subject to such adaptations and modifications as may be specified in the regulations, to works on land carried out, or uses of land begun, at any time before the appointed day, in accordance with permission granted subject to conditions under any enactment repealed by the Act of 1947, other than the enactments relating to town and country planning; and for the purposes of this provision any works or use in respect of which a notice was served under subsection (1) of section 1 of the M3Restriction of Ribbon Development (Temporary Development) Act 1943 or was deemed by virtue of subsection (4) of that section to have been so served, shall be treated as carried out or begun in accordance with permission granted subject to a condition restricting the period for which the works or use might be continued on the land.

Textual Amendments

Marginal Citations

SCHEDULES

SCHEDULE 22S Transitional Provisions and Savings

Part XVIS Miscellaneous and Supplementary

Development authorised under enactments repealed by Act of 1947S

76(1)Where any works on land existing at the appointed day, or any use to which land was put on that day, had been authorised by a permission granted subject to conditions under a scheme under the M1Town and Country Planning (Scotland) Act 1932 (or under an enactment repealed by that Act) or under an order made under section 10(1) of that Act (in the subsequent provisions of this Schedule referred to as “a planning scheme” and “an interim development order”) the provisions of Parts III and V of this Act, the provisions of Part IX of this Act relating to purchase notices, and the provisions of sections 214 to 217 of this Act, shall apply in relation to those works or that use as if the conditions had been imposed on the grant of planning permission.

(2)Without prejudice to the generality of sub-paragraph (1) of this paragraph, where any such permission was granted subject to conditions (in whatever form) restricting the period for which the works or use might be continued on the land, then, if that period had not expired at the appointed day and the works were or are not removed, or the use discontinued, at the end of that period, the provisions of Part V of this Act relating to enforcement notices shall apply in relation thereto as if the works had been carried out, or the use begun, as the case may be, at the end of that period and without the grant of planning permission in that behalf.

(3)The power of a F1 planning authority under Part III of this Act to grant permission for the retention on land of buildings or works constructed or carried out before the date of the application, or the continuance of any use of land instituted before that date, shall include power to grant such permission in respect of any works or use authorised by a permission granted subject to any such conditions as are mentioned in sub-paragraph (2) of this paragraph.

(4)Where at any time before the appointed day it was determined under the M2Building Restrictions (War-Time Contraventions) Act 1946 that any works on land or any use of land should be deemed to comply with planning control (within the meaning of that Act) subject to any conditions specified in the determination, the provisions of this paragraph shall apply in relation to those works or that use as if those conditions had been imposed on the grant of permission under a planning scheme or an interim development order.

(5)Provisions may be made by regulations under this Act for applying the preceding provisions of this paragraph, subject to such adaptations and modifications as may be specified in the regulations, to works on land carried out, or uses of land begun, at any time before the appointed day, in accordance with permission granted subject to conditions under any enactment repealed by the Act of 1947, other than the enactments relating to town and country planning; and for the purposes of this provision any works or use in respect of which a notice was served under subsection (1) of section 1 of the M3Restriction of Ribbon Development (Temporary Development) Act 1943 or was deemed by virtue of subsection (4) of that section to have been so served, shall be treated as carried out or begun in accordance with permission granted subject to a condition restricting the period for which the works or use might be continued on the land.

Textual Amendments

Marginal Citations