Point in time view as at 01/10/2004.

Changes to legislation:

Reservoirs Act 1975, Cross Heading: Supplementary is up to date with all changes known to be in force on or before 29 July 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

SupplementaryE+W+S

19 Reference of disputed recommendations to referee. E+W+S

(1)Where—

(a)an inspecting engineer includes in his report recommendations as to measures to be taken in the interests of safety or as to the time of the next inspection; or

(b)an engineer acting under section 8, 9 or 14 above includes in his report recommendations as to measures to be taken in the interests of safety;

the undertakers if aggrieved by any recommendation may, in accordance with rules under this section, refer their complaint to a referee.

(2)A referee under this section shall be an independent qualified civil engineer appointed by agreement between the undertakers and the engineer making the recommendation complained of, or in default of their agreement shall be a person appointed by the Secretary of State.

(3)A referee under this section, after investigating the complaint, shall have power to make such modifications as he thinks fit in the report containing the recommendation complained of, and the report shall for the purposes of this Act have effect accordingly.

(4)A referee under this section, when he gives his decision on a report, shall also give a certificate stating that the decision does or does not modify the report, and (if necessary in consequence of any modification) revising accordingly any certificate given with reference to the report by the engineer making the report.

(5)The Secretary of State may by statutory instrument make rules as to the time within which a referee may be appointed by agreement under this section, as to the time within which, and the manner in which, a request for the appointment of a referee under this section may be made to him, as to the procedure before the referee and as to the costs of the proceedings before and investigation by the referee (including the remuneration of the referee), so, however, that those costs (including the remuneration of the referee) shall be paid by the undertakers.

Modifications etc. (not altering text)

C1Ss. 19, 20 modified by S.I. 1986/466, art. 2(2), Sch. 1

20 General provisions as to reports, certificates etc. of engineers. E+W+S

(1)Any report or certificate of an engineer acting for any purpose of this Act, including a referee under section 19 above, shall be in the prescribed form.

(2)Any such report or certificate, unless the engineer in question is appointed to act by the enforcement authority, shall be delivered to and kept by the undertakers.

(3)Any such report or certificate, where the engineer in question is appointed to act by the enforcement authority, shall be delivered to the authority, but a copy of it shall be sent by the engineer at the same time to the undertakers and shall be kept by them.

(4)Where any document to which this subsection applies is delivered by the engineer in question to the undertakers, the engineer shall within twenty-eight days after he delivers it to the undertakers send a copy of it to the enforcement authority.

The documents to which this subsection applies are—

(a)any certificate of an engineer acting for any purpose of this Act;

(b)any report made by an inspecting engineer or an engineer acting for purposes of section 14 above and stated in his certificate to include a recommendation as to measures to be taken in the interests of safety, and any report made by an engineer acting under section 8 or 9 above;

(c)any decision of a referee modifying any such report as is mentioned in paragraph (b) above;

(d)any written explanation given by a construction engineer to the undertakers of his reasons for deferring the issue of his final certificate;

(e)any advice given by a supervising engineer to the undertakers which either—

(i)recommends them to have the reservoir inspected under section 10 above or to take any other action; or

(ii)draws their attention to a breach of any provision of section 6(2) to (4) or 9(2) or of section 11 above.

(5)Where an enforcement authority receive a certificate of an engineer acting for the purposes of section 13 above or a copy of such a certificate, and the reservoir is situated partly in the area of another [F1 relevant authority ] not being the undertakers, the enforcement authority shall send a copy of the certificate to that other [F1 relevant authority ].

Textual Amendments

F1Words in s. 20 substituted (1.10.2004) by Water Act 2003 (c. 37), ss. 74(1)(b), 105(3); S.I. 2004/2528, art. 2(k) (with Sch. para. 8)

Modifications etc. (not altering text)

C2Ss. 19, 20 modified by S.I. 1986/466, art. 2(2), Sch. 1

21 Duty of undertakers to furnish information. E+W+S

(1)Where undertakers intend—

(a)to construct a large raised reservoir (whether as a new reservoir or by alteration of an existing reservoir that is not a large raised reservoir), or to alter a large raised reservoir so as to increase its capacity; or

(b)to bring a large raised reservoir back into use as a reservoir after that use has been abandoned;

the undertakers, if they are not a [F2 relevant authority ], shall serve notice of their intention, giving the prescribed information, on the [F2 relevant authority ] in whose area the intended large raised reservoir will be or, if it will extend into the areas of more than one [F2 relevant authority ], on each of those authorities; and if the undertakers are a [F2 relevant authority ] and the reservoir or any part of it will be in the area of another [F2 relevant authority ] or authorities, they shall serve notice of their intention on the other authority or authorities.

A notice under this subsection shall be served not less than twenty-eight days before any work on the construction or alteration of the reservoir is begun or, if the case is within paragraph (b) above and the reservoir is to be brought back into use without alteration, not less than twenty-eight days before it is brought back into use.

(2)Where the use of a large raised reservoir as a reservoir is abandoned, the undertakers shall within twenty-eight days notify the enforcement authority in writing.

(3)Whenever a person is appointed to be, or ceases to be, supervising engineer for a large raised reservoir, the undertakers shall within twenty-eight days notify the enforcement authority in writing; and the notice of an appointment shall include the date on which the appointment will take effect, if it has not done so.

(4)On the appointment of an inspecting engineer for a large raised reservoir the undertakers shall within twenty-eight days notify the enforcement authority in writing of the appointment.

(5)The supervising engineer and every inspecting engineer for a large raised reservoir, and any civil engineer employed by the undertakers for purposes of section 8, 9, 10(6) or 14 above or appointed by an enforcement authority under section 15(2) or 16(3), shall be afforded by the undertakers all reasonable facilities for the effective performance of his functions; and the undertakers shall furnish him—

(a)with the statutory record required to be kept for the reservoir; and

(b)with copies of any statutory certificates relating to the reservoir, with their annexes (if any); and

(c)with copies of the reports made by inspecting engineers on any statutory inspection of the reservoir; and

(d)with such further information and particulars as he may require

(6)In this section “statutory” refers to matters provided for by this Act or by the M1Reservoirs (Safety Provisions) Act 1930.

Textual Amendments

F2Words in s. 21 substituted (1.10.2004) by Water Act 2003 (c. 37), ss. 74(1)(b), 105(3); S.I. 2004/2528, art. 2(k) (with Sch. para. 8)

Modifications etc. (not altering text)

C3S. 21 modified by S.I. 1985/176, art. 2(3)(ii), Sch. and 1986/466, art. 2(2), Schs. 1, 2

Marginal Citations

22 Criminal liability of undertakers and their employees. E+W+S

(1)If—

(a)by the wilful default of the undertakers any of the provisions of section 6, 8(3), 9(1), (2) or (3), 10(1) or (6), 11, 12(1), 13 or 14(1) or (2) above is not observed or complied with in relation to a large raised reservoir; [F3or]

(b)the undertakers fail to comply with a notice from the enforcement authority under section 8, 9, 10, 12 or 14 above;

then unless there is reasonable excuse for the default or failure, the undertakers shall be guilty of an offence and liable on conviction on indictment or on summary conviction to a fine, which on summary conviction shall not exceed £400.

[F4(c)the undertakers fail to comply with a direction under section 12A above;]

[F5(1A)If the undertakers fail without reasonable excuse to comply with a notice under section 12B above, they shall be guilty of an offence and liable—

(a)on summary conviction, to a fine not exceeding the statutory maximum;

(b)on conviction on indictment, to imprisonment for a term not exceeding two years, or to a fine, or to both.]

(2)If, in the case of any large raised reservoir, the undertakers fail without reasonable excuse to give the enforcement authority in due time any notice required by this Act to be given by them to that authority, the undertakers shall be guilty of an offence and liable on summary conviction to a fine not exceeding [F6level 4 on the standard scale].

(3)If, in the case of any large raised reservoir, the undertakers or persons employed by them without reasonable excuse refuse or knowingly fail to afford to any person the facilities required by section 21(5) above or to furnish to any person the information and particulars so required, the undertakers shall be guilty of an offence and liable on summary conviction to a fine not exceeding [F6level 4 on the standard scale].

(4)If for purposes of section 21(5) above a person makes use of any document or furnishes any information or particulars which he knows to be false in a material respect, or recklessly makes use of any document or furnishes any information or particulars which is or are false in a material respect, he shall be guilty of an offence and liable on summary conviction to a fine not exceeding [F6level 5 on the standard scale].

(5)Where an offence committed by a body corporate under this section is proved to have been committed with the consent or connivance of any director, manager, secretary or other similar officer of the body corporate, or any person who was purporting to act in any such capacity, he as well as the body corporate shall be guilty of that offence, and shall be liable to be proceeded against and punished accordingly.

Where the affairs of a body corporate are managed by its members, this section shall apply in relation to the acts and defaults of a member in connection with his functions of management as if he were a director of the body corporate.

(6)In England and Wales proceedings for an offence under this section may be instituted [F7 only by the Environment Agency or ] the Secretary of State or by or with the consent of the Director of Public Prosecutions.

Textual Amendments

F3Word in s. 22(1)(a) repealed (E.W.) (1.10.2004) by Water Act 2003 (c. 37), ss. 79(2), 105(3), Sch. 9 Pts. 3; S.I. 2004/2528, art. 2(o)(u)

F4S. 22(1)(c) inserted (E.W.) (1.10.2004) by Water Act 2003 (c. 37), ss. 79(2), 105(3); S.I. 2004/2528, art. 2(o) (with Sch. para. 8)

F5S. 22(1A) inserted (E.W.) (1.10.2004) by Water Act 2003 (c. 37), ss. 79(3), 105(3); S.I. 2004/2528, art. 2(o) (with Sch. para. 8)

F7Words in s. 22(6) substituted (1.10.2004) by Water Act 2003 (c. 37), ss. 74(1)(d), 105(3); S.I. 2004/2528, art. 2(k) (with Sch. para. 8)

Modifications etc. (not altering text)

C4S. 22 modified by S.I. 1985/176, art. 2(3)(ii), Sch. and 1986/466, art. 2(2), Schs. 1, 2

[F822AService of notices by the Environment AgencyE+W+S

Section 123 of the Environment Act 1995 (service of documents) applies to any document authorised or required by virtue of any provision of this Act to be served or given by the Environment Agency as if it were authorised or required to be served or given by or under that Act.]

Textual Amendments

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources