![Close](/images/chrome/closeIcon.gif)
Print Options
PrintThe Whole
Act
PrintThe Whole
Part
PrintThis
Cross Heading
only
Changes over time for: Cross Heading: Recovery by highway authorities etc. of certain expenses incurred in maintaining highways
![Help about opening options](/images/chrome/helpIcon.gif)
![Close](/images/chrome/closeIcon.gif)
Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Version Superseded: 22/04/2014
Status:
Point in time view as at 13/11/2012.
Changes to legislation:
Highways Act 1980, Cross Heading: Recovery by highway authorities etc. of certain expenses incurred in maintaining highways is up to date with all changes known to be in force on or before 17 February 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.![Help about Changes to Legislation](/images/chrome/helpIcon.gif)
![Close](/images/chrome/closeIcon.gif)
Changes to Legislation
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Recovery by highway authorities etc. of certain expenses incurred in maintaining highwaysE+W
59 Recovery of expenses due to extraordinary traffic.E+W
(1)Subject to subsection (3) below, where it appears to the highway authority for a highway maintainable at the public expense, by a certificate of their proper officer, that having regard to the average expense of maintaining the highway or other similar highways in the neighbourhood extraordinary expenses have been or will be incurred by the authority in maintaining the highway by reason of the damage caused by excessive weight passing along the highway, or other extraordinary traffic thereon, the highway authority may recover from any person (“the operator”) by or in consequence of whose order the traffic has been conducted the excess expenses.
(2)In subsection (1) above “the excess expenses” means such expenses as may be proved to the satisfaction of the court having cognizance of the case to have been or to be likely to be incurred by the highway authority by reason of the damage arising from the extraordinary traffic; and for the purposes of that subsection the expenses incurred by a highway authority in maintaining a highway are (without prejudice to the application of this section to a by-pass provided under this Act for use in connection with a cattle-grid) to be taken to include expenses incurred by them in maintaining a cattle-grid provided for the highway under this Act.
(3)If before traffic which may cause such damage commences the operator admits liability in respect of such traffic, then—
(a)the operator and the highway authority may agree for the payment by the operator to the highway authority of a sum by way of a composition of such liability, or
(b)either party may require that the sum to be so paid shall be determined by arbitration;
and where a sum has been so agreed or determined the operator is liable to pay that sum to the highway authority and is not liable to proceedings for the recovery of the excess expenses under subsection (1) above.
(4)[The county court with jurisdiction to hear and determine a claim for a sum recoverable under this section is] the county court in the district in which the highway or any part of it is situated.
(5)Proceedings for the recovery of any sums under this section shall be commenced within 12 months from the time at which the damage has been done or, where the damage is the consequence of any particular building contract or work extending over a long period, not later than 6 months from the date of completion of the contract or work.
(6)In the application of this section to highways for which the Minister is the highway authority the words “by a certificate of their proper officer” in subsection (1) are to be omitted.
60. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .E+W