SCHEDULES
SCHEDULE 16
Particulars to be Stated in Specifications, Notices, Etc., Under the Private Street Works Code
1
The specification shall describe generally the works and things to be done, and, in the case of structural works, shall specify so far as may be practicable the foundation, form, material and dimensions thereof.
2
The plans and sections shall show the constructional character of the works, the connections (if any) with existing streets, sewers or other works, and the lines and levels of the works, subject to such limits of deviation (if any) as may be indicated on the plans and sections respectively.
3
The estimate shall show the particulars of the probable cost of the whole works, including any additional charge in respect of surveys, superintendence and notices.
4
The provisional apportionment shall state the amounts charged on the respective premises and the names of the respective owners, or reputed owners, and shall also state whether the apportionment is made according to the frontage of the respective premises or not, and the measurements of the frontages, and the other considerations (if any) on which the apportionment is based.
5
The notice under section 205 of this Act shall contain the following particulars:—
a
a statement that the street works authority have resolved to execute street works in the private street in question;
b
the address of the offices of the authority at which a copy of the resolution of approval, and the approved documents or copies of them certified by the proper officer, may be inspected, and the times at which, and the period during which, they may be inspected; and
c
a statement that an owner of premises liable to be charged with any part of the expenses of executing the street works may object to the proposal to execute the works, giving the period during which such objection may be made.
6
The notice under section 210 of this Act shall contain the following particulars:—
a
a statement that the street works authority propose to amend the estimate so as to increase the amount of it, specifying the former amount and the amount to which it is to be increased;
b
the address of the offices of the authority at which a document certified by the proper officer giving details of the proposed amendment and of the proposed consequential amendment of the provisional apportionment may be inspected, and the times at which, and the period during which, it may be inspected; and
c
a statement that an owner of premises liable to be charged with any part of the expenses of executing the street works may object to the proposed amendments, giving the period during which such objection may be made.