SCHEDULES

[F1SCHEDULE A1E+WCounter-notice requiring purchase of land not in general vesting declaration

Textual Amendments

Modifications etc. (not altering text)

C1Sch. A1 excluded by 2017 c. 7, s. 7(2) (as amended) (24.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(2), Sch. 14 para. 2; S.I. 2017/209, reg. 2

C2Sch. A1 excluded by 2017 c. 7, s. 8(2) (as amended) (24.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(2), Sch. 14 para. 3; S.I. 2017/209, reg. 2

C17Sch. A1 excluded (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 25(3)(b) (with arts. 7, 25(4))

PART 3E+WDetermination by the Upper Tribunal

Effect of determination that more land should be acquiredE+W

16(1)This paragraph applies where the Upper Tribunal specifies in its determination that the acquiring authority ought to be required to take the whole or part of the additional land (“the specified land”).E+W

(2)The general vesting declaration and any notice to treat (and, where applicable, the compulsory purchase order) are to have effect as if they included the owner's interest in the specified land.

(3)The Upper Tribunal must order a vesting date for—

(a)the specified land, and

(b)any land proposed to be acquired which has not vested in the authority and for which no vesting date has been specified under paragraph 12.

[F2(4)If the vesting date for the specified land is after the vesting date for any land proposed to be acquired, the Upper Tribunal's power to award compensation under section 7 of the Compulsory Purchase Act 1965 includes power to award compensation for any loss suffered by the owner by reason of the temporary severance of the land proposed to be acquired from the specified land.]]

Textual Amendments

F2Sch. A1 para. 16(4) inserted (19.7.2017) by Neighbourhood Planning Act 2017 (c. 20), ss. 41, 46(1); S.I. 2017/767, reg. 2(j)