Point in time view as at 13/07/2016.
Acquisition of Land Act 1981, Part IV is up to date with all changes known to be in force on or before 01 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Modifications etc. (not altering text)
C1Parts II-IV applied (31.10.1994) by Opencast Coal Act 1958 c. 69, s. 16(4A) as substituted (31.10.1994) by 1994 c. 21, s. 52, Sch. 8 para. 14(5) (with s. 40(7)); S.I. 1994/2553, art. 2
(1)If any person aggrieved by a compulsory purchase order desires to question the validity thereof, or of any provision contained therein, on the ground that the authorisation of a compulsory purchase thereby granted is not empowered to be granted under this Act or any such enactment as is mentioned in section 1(1) of this Act, he may make an application to the High Court.
(2)If any person aggrieved by—
(a)a compulsory purchase order, or
(b)a certificate under Part III of, or Schedule 3 to, this Act,
desires to question the validity thereof on the ground that any relevant requirement has not been complied with in relation to the order or certificate he may make an application to the High Court.
(3)In subsection (2) above “relevant requirement” means—
(a)any requirement of this Act, or of any regulation under section 7(2) above, or
(b)any requirement of the M1Tribunals and Inquiries Act [F11992] or of any rules made, or having effect as if made, under that Act.
(4)An application to the High Court under this section shall be made within six weeks—
(a)in the case of a compulsory purchase order to which the M2Statutory Orders (Special Procedure) Act 1945 applies (and which is not excluded by section 27 below), from the date on which the order becomes operative under that Act,
(b)in the case of a compulsory purchase order to which the said Act of 1945 does not apply, from the date on which notice of the confirmation or making of the order is first published in accordance with this Act,
(c)in the case of a certificate, the date on which notice of the giving of the certificate is first published in accordance with this Act.
Textual Amendments
F1Word in s. 23(3)(b) substituted (1. 10. 1992) by Tribunals and Inquiries Act 1992 (c. 53), ss. 18(1), 19(2), Sch. 3 para.14.
Marginal Citations
M21945 (9 & 10 Geo 6) c. 18.
(1)On an application under section 23 above the court may by interim order suspend the operation of the compulsory purchase order or any provision contained therein, or of the certificate, either generally or in so far as it affects any property of the applicant, until the final determination of the proceedings.
(2)If on the application the court is satisfied that—
(a)the authorisation granted by the compulsory purchase order is not empowered to be granted under this Act or any such enactment as is mentioned in section 1(1) of this Act, or
(b)the interests of the applicant have been substantially prejudiced by any relevant requirement (as defined in section 23(3) above) not having been complied with,
the court may quash the compulsory purchase order or any provision contained therein, or the certificate, either generally or in so far as it affects any property of the applicant.
[F2(3)If the court has power under subsection (2) to quash a compulsory purchase order it may instead quash the decision to confirm the order either generally or in so far as it affects any property of the applicant.]
Textual Amendments
F2S. 24(3) inserted (13.7.2016) by Housing and Planning Act 2016 (c. 22), ss. 201, 216(3); S.I. 2016/733, reg. 3(k) (with reg. 8)
Subject to the preceding provisions of this Part of this Act, a compulsory purchase order, or a certificate under Part III of, or Schedule 3 to, this Act, shall not, either before or after it has been confirmed, made or given, be questioned in any legal proceedings whatsoever.
(1)Subject to section 24 above, a compulsory purchase order, other than one to which the M3Statutory Orders (Special Procedure) Act 1945 applies, shall become operative on the date on which notice of the confirmation or making of the order is first published in accordance with this Act.
(2)Subject to section 24 above, a certificate under Part III of, or Schedule 3 to, this Act shall become operative on the date on which notice of the giving of the certificate is first published in accordance with this Act.
Marginal Citations
M31945 (9 & 10 Geo 6) c. 18.
This Part of this Act shall not apply to an order which is confirmed by Act of Parliament under section [F34 or] 6 of the M4Statutory Orders (Special Procedure) Act 1945.
Textual Amendments
F3Words in s. 27 inserted (25.6.2013) by Growth and Infrastructure Act 2013 (c. 27), ss. 25(9), 35(1); S.I. 2013/1488, art. 3(e) (with art. 8(3))
Marginal Citations
M41945 (9 & 10 Geo 6) c. 18.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: