SCHEDULES

C5C17SCHEDULE 2 Minerals

Annotations:
Modifications etc. (not altering text)
C5

Sch. 2 excluded by Water Act 1989 (c. 15, SIF 130), s. 159, (with ss. 58(7), 101(1), 141(6), 160(1)(2)(4), 163, 189(4)–(10), 190, 193(1), Sch. 26 paras. 3(1)(2), 17, 40(4), 57(6), 58)

Sch. 2 excluded (1.12.1991) by Water Resources Act 1991 (c. 57, SIF 130), ss.182, 225(2) (with ss. 16(6), 179, 222(3), Sch. 22 para. 1, Sch. 23 para. 6)

C6C7C6C7

C1C2C3C4C8C9C11C10C12C13C14C15C16C18C19C20C21C22C23C31C24C25C26C27C28C30C29 Part III

Annotations:
Modifications etc. (not altering text)
C2

Sch. 2 Pts. 2, 3 applied (with modifications) by Dartford-Thurrock Crossing Act 1988 (c. 20, SIF 59), s. 2(5), Sch. 2 Pt. 2 para. 4(1)

Sch. 2 Pt. 3 applied (with modifications) (28.7.1998) by 1998 c. iv, s. 7(1)(2)(with s. 41)

Sch. 2 Pts. 2, 3 applied (with modifications) (3.6.1999) by S.I. 1999/1555, art. 9

Sch. 2 Pt. 3 applied (with modifications) (E.) (29.3.2001) by S.I. 2001/1347, art. 36(1) (with arts. 15, 37, 38(2))

Sch. 2 Pt. 3 applied (with modifications) (E.) (29.3.2001) by S.I. 2001/1348, art. 12(1)

C3

Sch. 2 Pt. 3 modified (18.12.1996) by 1996 c. 61, s. 4, Sch. 4 Pt. 3 para. 13

C4

Sch. 2 Pt. 3 applied (with modifications) (12.8.2002) by The Channel Tunnel Rail Link (Thames Tunnel Approach) Order 2002 (S.I. 2002/1943), art. 6(2)

Sch. 2 Pt. 3 applied (with modifications) (14.3.2002) by The Chester Guided Busway Order 2002 (S.I. 2002/412), art. 39(1) (with art. 38)

C9

Sch. 2 Pts. 2, 3 applied (with modifications) (22.7.2005) by The Midland Metro (Birmingham City Centre Extension, etc.) Order 2005 (S.I. 2005/1794), arts. 1, 46(1) (with art. 47)

C11

Sch. 2 Pt. 3 applied (with modifications) (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 6 para. 17

C10

Sch. 2 Pt. 3 applied (with modifications) (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 3 para. 3(5)

C12

Sch. 2 Pts. 2, 3 incorporated (with modifications) (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 14 (with art. 30)

C13

Sch. 2 Pt. 3 incorporated (with modifications) (7.5.2014) by The National Grid (North London Reinforcement Project) Order 2014 (S.I. 2014/1052), arts. 1, 23

Sch. 2 Pt. 3 incorporated (with modifications) (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 40

C14

Sch. 2 Pts. 1-3 applied (with modifications) (2.10.2014) by The Clocaenog Forest Wind Farm Order 2014 (S.I. 2014/2441), arts. 1, 22 (with art. 33)

C15

Sch. 2 Pt. 3 incorporated (with modifications) (29.10.2014) by The Able Marine Energy Park Development Consent Order 2014 (S.I. 2014/2935), art. 32 (with arts. 30(4), 53)

C18

Sch. 2 Pts. 2, 3 incorporated (with modifications) (9.6.2015) by The White Moss Landfill Order 2015 (S.I. 2015/1317), arts. 1, 13 (with art. 5)

C20

Sch. 2 Pts. 2, 3 incorporated in part (with modifications) (14.8.2015) by The Hirwaun Generating Station Order 2015 (S.I. 2015/1574), arts. 1, 17(1) (with art. 30)

C21

Sch. 2 Pt. 3 incorporated in part (with modifications) (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 14 (with art. 26)

C22

Sch. 2 Pts. 2, 3 incorporated (with modifications) (2.2.2016) by The East Midlands Gateway Rail Freight Interchange and Highway Order 2016 (S.I. 2016/17), arts. 1, 27

C23

Sch. 2 Pt. 3 incorporated in part (with modifications) (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 20 (with art. 32)

C31

Sch. 2 Pts. II, III incorporated (with modifications) (25.3.2016) by The Thorpe Marsh Gas Pipeline Order 2016 (S.I. 2016/297), arts. 1, 21

C24

Sch. 2 Pts. 2, 3 incorporated (with modifications) (1.6.2016) by The A14 Cambridge to Huntingdon Improvement Scheme Development Consent Order 2016 (S.I. 2016/547), arts. 1, 21 (with arts. 4, 5(3))

C26

Sch. 2 Pts. 2, 3 incorporated (with modifications) (10.8.2016) by The York Potash Harbour Facilities Order 2016 (S.I. 2016/772), arts. 1, 26 (with arts. 35, 36)

C27

Sch. 2 Pts. 2, 3 incorporated (with modifications) (15.9.2016) by The River Humber Gas Pipeline Replacement Order 2016 (S.I. 2016/853), arts. 1, 37 (with art. 43)

C28

Sch. 2 Pts. 2, 3 incorporated in part (with modifications) (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 33

4

1

If before the expiration of 30 days from the receipt of notice under paragraph 3(1) above the acquiring authority do not state their willingness to treat with the owner for the payment of compensation the owner may work any of the underlying mines for which the acquiring authority has not agreed to pay compensation by proper methods and in the usual manner of working such mines in the district in question.

2

If any damage or obstruction to the undertaking is caused by improper working of the underlying mines—

a

the owner of the mines shall forthwith repair or remove the damage or obstruction at his own expense,

b

the acquiring authority may, without waiting for the owner to perform his duty, or in case of his default, repair or remove the damage or obstruction and recover their expenses from the owner in proceedings in the High Court.