Acquisition of Land Act 1981, Part II is up to date with all changes known to be in force on or before 01 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Modifications etc. (not altering text)
C1Sch. 2 Pts. 2, 3 applied (with modifications) (22.3.2005) by The Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), art. 50 (with art. 51)
C2Sch. 2 Pts. 2, 3 applied (with modifications) (22.7.2005) by The Midland Metro (Birmingham City Centre Extension, etc.) Order 2005 (S.I. 2005/1794), arts. 1, 46(1) (with art. 47)
C3Sch. 2 Pt. 2 applied (with modifications) (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 6 para. 17
C4Sch. 2 Pts. 2, 3 incorporated (with modifications) (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 14 (with art. 30)
C5Sch. 2 Pt. 2 incorporated (with modifications) (7.5.2014) by The National Grid (North London Reinforcement Project) Order 2014 (S.I. 2014/1052), arts. 1, 23
Sch. 2 Pt. 2 incorporated (with modifications) (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 40
C6Sch. 2 Pts. 1-3 applied (with modifications) (2.10.2014) by The Clocaenog Forest Wind Farm Order 2014 (S.I. 2014/2441), arts. 1, 22 (with art. 33)
C7Sch. 2 Pt. 2 incorporated (with modifications) (29.10.2014) by The Able Marine Energy Park Development Consent Order 2014 (S.I. 2014/2935), art. 32 (with arts. 30(4), 53)
C8Sch. 2 Pts. 2, 3 incorporated (with modifications) (2.2.2015) by The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015 (S.I. 2015/23), arts. 1, 21(1)
C9Sch. 2 Pt. 2 incorporated (with modifications) (25.2.2015) by The A160/A180 (Port of Immingham Improvement) Development Consent Order 2015 (S.I. 2015/129), arts. 1, 20
C10Sch. 2 Pt. 2 incorporated (with modifications) (1.4.2015) by The Knottingley Power Plant Order 2015 (S.I. 2015/680), arts. 1, 19 (with Sch. 8 para. 10)
C11Sch. 2 Pts. 2, 3 incorporated (with modifications) (9.6.2015) by The White Moss Landfill Order 2015 (S.I. 2015/1317), arts. 1, 13 (with art. 5)
C12Sch. 2 Pts. 2, 3 incorporated (with modifications) (23.6.2015) by The Norfolk County Council (Norwich Northern Distributor Road (A1067 to A47(T))) Order 2015 (S.I. 2015/1347), arts. 1, 21
C13Sch. 2 Pts. 2, 3 incorporated in part (with modifications) (14.8.2015) by The Hirwaun Generating Station Order 2015 (S.I. 2015/1574), arts. 1, 17(1) (with art. 30)
C14Sch. 2 Pt. 2 incorporated (with modifications) (26.8.2015) by The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (S.I. 2015/1592), arts. 1, 23 (with arts. 40, 41)
C15Sch. 2 Pt. 2 incorporated in part (with modifications) (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 14 (with art. 26)
C16Sch. 2 Pts. 2, 3 incorporated (with modifications) (2.2.2016) by The East Midlands Gateway Rail Freight Interchange and Highway Order 2016 (S.I. 2016/17), arts. 1, 27
C17Sch. 2 Pt. 2 incorporated in part (with modifications) (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 20 (with art. 32)
C18Sch. 2 Pts. 2, 3 applied by Channel Tunnel Act 1987 (c. 53, SIF 102), s. 37(2), Sch. 5 Pt. III para. 4
C19Sch. 2 Pts. 2, 3 applied (with modifications) (13.2.1992) by Severn Bridges Act 1992 (c. 3), s. 2(6), Sch. 2 Pt. II para.3
C20Sch. 2 Pt. 2 applied (16.3.1992) by Avon Weir Act 1992 (c. v), s. 4(2) (with s. 61)
C21Sch. 2 Pts. 2, 3 applied (16.7.1992) by Cattewater Reclamation Act 1992 (c. xiv), s. 3(3)
Sch. 2 Pts. 2, 3 applied (5.11.1993) by 1993 c. 42, s. 5, Sch. 4 para. 2 (with s. 30(1), Sch. 2 para. 9).
Sch. 2 Pt. 2 applied (28.7.1998) by 1998 c. iv, s. 7(1) (with s. 41)
C22Sch. 2 Pts. 2, 3 applied (with modifications) by Dartford-Thurrock Crossing Act 1988 (c. 20, SIF 59), s. 2(5), Sch. 2 Pt. II para. 4(1)
Sch. 2 Pts. 2, 3 applied (with modifications) (3.6.1999) by S.I. 1999/1555, art. 9
Sch. 2 Pt 2 applied (with modifications) (E.) (29.3.2001) by S.I. 2001/1347, art. 36(1) (with arts. 15, 37, 38(2))
Sch. 2 Pt. 2 applied (with modifications) (E.) (29.3.2001) by S.I. 2001/1348, art. 12(1)
C23Sch. 2 Pt. 2 modified (18.12.1996) by 1996 c. 61, s. 4, Sch. 4 Pt. III para. 13
C24Sch. 2 Pt. 2 applied (with modifications) (12.8.2002) by The Channel Tunnel Rail Link (Thames Tunnel Approach) Order 2002 (S.I. 2002/1943), art. 6(2)
Sch. 2 Pt. 2 applied (with modifications) (14.3.2002) by The Chester Guided Busway Order 2002 (S.I. 2002/412), art. 39(1) (with art. 38)
2(1)The acquiring authority shall not be entitled to any mines under the land comprised in the compulsory purchase order unless they have been expressly purchased, and all mines under the land shall be deemed to be excepted out of the conveyance of that land unless expressly named and conveyed.E+W
(2)Sub-paragraph (1) above shall not apply to minerals necessarily extracted or used in the construction of the undertaking.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: