Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Valid from 31/03/2003
Textual Amendments
F1Pt. 1B inserted (31.3.2003) by The Sale and Supply of Goods to Consumers Regulations 2002. S.I. 2002/3045, reg. 9
(1)This section applies if—
(a)the transferee deals as consumer or, in Scotland, there is a consumer contract in which the transferee is a consumer, and
(b)the goods do not conform to the contract for the transfer of goods at the time of delivery.
(2)If this section applies, the transferee has the right—
(a)under and in accordance with section 11N below, to require the transferor to repair or replace the goods, or
(b)under and in accordance with section 11P below—
(i)to require the transferor to reduce the amount to be paid for the transfer by the transferee by an appropriate amount, or
(ii)to rescind the contract with regard to the goods in question.
(3)For the purposes of subsection (1)(b) above, goods which do not conform to the contract for the transfer of goods at any time within the period of six months starting with the date on which the goods were delivered to the transferee must be taken not to have so conformed at that date.
(4)Subsection (3) above does not apply if—
(a)it is established that the goods did so conform at that date;
(b)its application is incompatible with the nature of the goods or the nature of the lack of conformity.
(5)For the purposes of this section, “consumer contract” has the same meaning as in section 11F(3) above.
(1)If section 11M above applies, the transferee may require the transferor—
(a)to repair the goods, or
(b)to replace the goods.
(2)If the transferee requires the transferor to repair or replace the goods, the transferor must—
(a)repair or, as the case may be, replace the goods within a reasonable time but without causing significant inconvenience to the transferee;
(b)bear any necessary costs incurred in doing so (including in particular the cost of any labour, materials or postage).
(3)The transferee must not require the transferor to repair or, as the case may be, replace the goods if that remedy is—
(a)impossible,
(b)disproportionate in comparison to the other of those remedies, or
(c)disproportionate in comparison to an appropriate reduction in the purchase price under paragraph (a), or rescission under paragraph (b), of section 11P(1) below.
(4)One remedy is disproportionate in comparison to the other if the one imposes costs on the transferor which, in comparison to those imposed on him by the other, are unreasonable, taking into account—
(a)the value which the goods would have if they conformed to the contract for the transfer of goods,
(b)the significance of the lack of conformity to the contract for the transfer of goods, and
(c)whether the other remedy could be effected without significant inconvenience to the transferee.
(5)Any question as to what is a reasonable time or significant inconvenience is to be determined by reference to—
(a)the nature of the goods, and
(b)the purpose for which the goods were acquired.
(1)If section 11M above applies, the transferee may—
(a)require the transferor to reduce the purchase price of the goods in question to the transferee by an appropriate amount, or
(b)rescind the contract with regard to those goods,
if the condition in subsection (2) below is satisfied.
(2)The condition is that—
(a)by virtue of section 11N(3) above the transferee may require neither repair nor replacement of the goods, or
(b)the transferee has required the transferor to repair or replace the goods, but the transferor is in breach of the requirement of section 11N(2)(a) above to do so within a reasonable time and without significant inconvenience to the transferee.
(3)If the transferee rescinds the contract, any reimbursement to the transferee may be reduced to take account of the use he has had of the goods since they were delivered to him.
(1)If the transferee requires the transferor to repair or replace the goods the transferee must not act under subsection (2) until he has given the transferor a reasonable time in which to repair or replace (as the case may be) the goods.
(2)The transferee acts under this subsection if—
(a)in England and Wales or Northern Ireland he rejects the goods and terminates the contract for breach of condition;
(b)in Scotland he rejects any goods delivered under the contract and treats it as repudiated; or
(c)he requires the goods to be replaced or repaired (as the case may be).
(1)In any proceedings in which a remedy is sought by virtue of this Part the court, in addition to any other power it has, may act under this section.
(2)On the application of the transferee the court may make an order requiring specific performance or, in Scotland, specific implement by the transferor of any obligation imposed on him by virtue of section 11N above.
(3)Subsection (4) applies if—
(a)the transferee requires the transferor to give effect to a remedy under section 11N or 11P above or has claims to rescind under section 11P, but
(b)the court decides that another remedy under section 11N or 11P is appropriate.
(4)The court may proceed—
(a)as if the transferee had required the transferor to give effect to the other remedy, or if the other remedy is rescission under section 11P,
(b)as if the transferee had claimed to rescind the contract under that section.
(5)If the transferee has claimed to rescind the contract the court may order that any reimbursement to the transferee is reduced to take account of the use he has had of the goods since they were delivered to him.
(6)The court may make an order under this section unconditionally or on such terms and conditions as to damages, payment of the price and otherwise as it thinks just.
(1)Goods do not conform to a contract for the supply or transfer of goods if—
(a)there is, in relation to the goods, a breach of an express term of the contract or a term implied by section 3, 4 or 5 above or, in Scotland, by section 11C, 11D or 11E above, or
(b)installation of the goods forms part of the contract for the transfer of goods, and the goods were installed by the transferor, or under his responsibility, in breach of the term implied by section 13 below or (in Scotland) in breach of any term implied by any rule of law as to the manner in which the installation is carried out.]
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: