Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Subject to, subsections (2) and (3) below, the Secretary of State, F1. . ., may construct new trunk and other roads.
(2)Without prejudice to section 5(4) and (5) of this Act, before constructing a road other than a trunk road under subsection (1) above, the Secretary of State shall consult every local roads authority in whose area any part of the road will be situated and shall consider any objections to the road which he may receive from them.
(3)Without prejudice to section 7(3) and (5)(a) of this Act, the “other roads” referred to in subsection (1) above do not include special roads.
Textual Amendments
F1Words in s. 19(1) repealed (1.7.1999) by S.I. 1999/1820, arts. 1(2), 4, Sch. 2 Pt. I para. 76(1)(3), Pt. IV (with art. 5)
(1)Without prejudice to section 7(3) and (5)(a) of this Act, a local roads authority may construct in their area any new road, other than a special road, which they consider requisite.
(2)When such construction by them as is mentioned in subsection (1) above or in the said section 7(5)(a) is completed, the local roads authority shall enter the road (or as the case may be special road) in their list of public roads.
Modifications etc. (not altering text)
C1S. 20(2) extended by S.I. 1985/2080, reg. 14(b)
(1)If the Scottish Ministers have under consideration the construction of a new road for which they are the roads authority they shall before details of the project are published, determine whether or not it falls within Annex I or II.
(2)If the Scottish Ministers determine that the project–
(a)falls within Annex I, or
(b)is a relevant project falling within Annex II and that having regard to the selection criteria contained in Annex III it should be made subject to an environmental impact assessment in accordance with the Directive,
they shall, not later than the date when details of the project are published, publish an environmental statement.
(3)The Scottish Ministers shall publish any determination made by them in accordance with subsection (2) above.
(4)Any project for the construction of a special road which falls within Annex II shall be treated as having characteristics that require it to be made subject to an environmental impact assessment.
(5)The Scottish Ministers shall publish any environmental statement so as to ensure that members of the public who are likely to be concerned are given a reasonable opportunity to express an opinion before they decide whether to proceed with the project, and they shall not make any such decision without taking into consideration any opinion so expressed to them within a period of 3 weeks from the date of publication of the environmental statement.
(6)The Scottish Ministers shall ensure that the consultation bodies are given an opportunity to express an opinion on the published details of the project and the environmental statement before they decide whether to proceed with the project.
(7)Subject to subsection (8) below, to the extent to which the Scottish Ministers consider that–
(a)it is relevant to the specific characteristics of the project and of the environmental features likely to be affected by it, and
(b)having regard in particular to current knowledge and methods of assessment, the information may reasonably be gathered,
the environmental statement published in accordance with subsection (2) above shall contain the information referred to in Annex IV.
(8)The environmental statement published in accordance with subsection (2) above shall contain at least the following information–
(a)a description of the project comprising information on the site, design and size of the project;
(b)a description of the measures envisaged in order to avoid, reduce and, if possible, remedy significant adverse effects;
(c)the data required to identify and assess the main effects which the project is likely to have on the environment;
(d)an outline of the main alternatives studied by the Scottish Ministers and an indication of the main reason for their choice (taking into account the environmental effects); and
(e)a non-technical summary of the information mentioned in paragraphs (a) to (d).
(9)In this section and section 20B of this Act–
“the Directive” means Council Directive No. 85/337/EEC on the assessment of the effects of certain public and private projects on the environment as amended by Council Directive No. 97/11/EC;
“Annex” means an Annex to the Directive;
“relevant project” means a project for the construction of a new road where the completed works (together with any area occupied by apparatus, equipment, machinery, materials, plant, spoil heaps or other such facilities or stores required during the period of construction)–
(a)exceed 1 hectare in area; or
(b)are situated in whole or in part in a sensitive area;
“sensitive area” shall have the meaning ascribed to that expression in regulation 2(1) of the Environmental Impact Assessment (Scotland) Regulations 1999.]
Textual Amendments
F2Ss. 20A and 20B substituted for s. 20A (1.8.1999) by S.S.I. 1999/1, reg. 49
(1)This section applies if–
(a)it appears to the Scottish Ministers that a project to which section 20A(2) of this Act applies is likely to have a significant effect on the environment in another EEA State; or
(b)an EEA State the environment of which is likely to be significantly affected by such a project asks the Scottish Ministers for information about it.
(2)The Scottish Ministers shall give to the EEA State–
(a)a description of the project together with any information available to them which suggests that it may have a significant effect on the environment in the EEA State;
(b)any information which they have about the nature of the decision which may be taken on the project;
(c)where they consider it appropriate, information about the environmental impact assessment procedure; and
(d)a reasonable period within which to indicate whether the EEA State wishes to participate in that procedure of this Act.
(3)Subsection (2)(a) and (b) above must be complied with no later than the date of publication of the notice referred to in section 20A(3) of this Act.
(4)If the EEA State indicates that it wishes to participate in the environmental impact assessment procedure, the Scottish Ministers shall give it–
(a)a copy of the environmental statement where that has not already been given to that EEA State; and
(b)any information about the environmental impact assessment procedure which they consider it appropriate to give and which has not already been made available to that EEA State.
(5)The Scottish Ministers shall also–
(a)arrange for the information which they have given to the EEA State to be made available within a reasonable time to–
(i)the authorities referred to in Article 6(1) of the Directive; and
(ii)members of the public in the EEA State who are likely to be concerned; and
(b)ensure that those authorities and the members of the public concerned are given a reasonable opportunity to express an opinion before they decide whether to proceed with the project.
(6)In accordance with Article 7(4) of the Directive, the Scottish Ministers shall–
(a)enter into consultation with the EEA State concerned regarding in particular the potential significant effects of the project on the environment of that EEA State and the measures envisaged to reduce or eliminate those effects; and
(b)agree with the EEA State a reasonable period for that consultation.
(7)Where an EEA State has been consulted in accordance with subsection (4) above, the Scottish Ministers shall inform the EEA State of the decision and give it copies of the documents referred to in paragraph 7(1B) or 13(1B) as the case may be of Schedule 1 to this Act.
(8)In this section “EEA State” means a State which is a Contracting Party to the Agreement on the European Economic Area signed at Oporto on 2nd May 1992 M1 as adjusted by the Protocol signed at Brussels on 17th March 1993 M2.]
Textual Amendments
F3Ss. 20A and 20B substituted for s. 20A (1.8.1999) by S.S.I. 1999/1, reg. 49
Marginal Citations
M1Cm 2073.
M2Cm 2183.
(1)A person other than a roads authority who wishes to construct a new road or an extension of an existing road shall before commencing such construction obtain the consent (in this section and in sections 22 and 23 of this Act referred to as “construction consent”) thereto of the local roads authority.
(2)An application for construction consent—
(a)shall be in writing in such from as the local roads authority may determine; and
(b)shall by notice be intimated by the applicant to—
(i)the owners of all land which would front, abut or be comprehended in the new road or the extension of the existing road; and
(ii)such other persons, if any, as the authority may, for the purposes of the application, specify..
(3)The local roads authority shall consider any written representations, made to them within 28 days of the date of intimation, by any person to whom an application has been intimated under subsection (2)(b) above, and may thereafter—
(a)subject to subsection (4) below, grant construction consent, either without conditions or subject to such conditions as they think fit; or
(b)refuse construction consent;
and before granting the consent subject to a condition (other than the condition mentioned in subsection (4) below) or refusing consent, the authority shall allow the person applying for the consent an opportunity to be heard by them as regards his application.
(4)It shall be a condition of any construction consent that the construction be completed within such period, being a period of not less than three years from the date on which the consent is given, as the local roads authority may specify in writing in the consent; but the authority may subsequently by notice extend the period so specified.
(5)Without prejudice to section 22(b) of this Act, where a condition imposed by a construction consent has been contravened or not complied with, the local roads authority may, by notice served on the person holding the consent, require him to bring the new road into conformity with the construction consent within such reasonable period as they shall specify in the notice.
(6)An applicant for construction consent may, within 28 days of the date of the intimation to him of a decision of the local roads authority—
(a)refusing his application; or
(b)granting it subject to conditions other than a condition that the construction be completed within 3 years of the date on which the consent was given,
appeal to the Secretary of State in accordance with the procedure prescribed by any regulations under subsection (7) below.
(7)The Secretary of State may by regulations prescribe the procedure to be followed in relation to an appeal to him under subsection (6) above, and such regulations may, without prejudice to the foregoing generality, make provision for the determination of any such appeal by a person appointed by the Secretary of State and for the powers and duties of such a person in that regard.
(8)The determination of an appeal under subsection (6) above may allow or dismiss the appeal, may modify any part of the decision of the local roads authority and shall be final.
Any person (other than a roads authority)—
(a)who constructs a new road or an extension of an existing road without construction consent; or
(b)who contravenes, or fails to comply with, a condition (other than such condition as is mentioned in section 21(4) of this Act) imposed by a construction consent,
commits an offence, which shall be triable either summarily or on indictment.
(1)The local roads authority may stop up or temporarily close any new road which another person (other than a roads authority) has constructed—
(a)without construction consent; or
(b)in contravention of, or non-compliance with, a condition imposed by a construction consent.
(2)Stopping up or temporary closure under subsection (1) above may take place whether or not proceedings are pending under section 22 of this Act but shall be ended if, in any such proceedings, it is found—
(a)in a case where the stopping up or closure took place on the basis that there was no construction consent, that there was such consent; or
(b)in any other case, that there was no contravention of, or failure to comply with, the construction consent condition to which the proceedings relate.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: