SCHEDULES

SCHEDULE 2 Validity and Date of Operation of Certain Orders and Schemes

1

As soon as may be after a scheme or order to which this Schedule applies has been made or confirmed by the Secretary of State F1(or where the order, scheme or instrument confirming the scheme is subject to the affirmative procedure by virtue of section 143A(3) of this Act, after a draft statutory instrument containing or confirming the order or scheme has been laid before the Scottish Parliament) , he shall publish in the Edinburgh Gazette, and in such other manner as he thinks best adapted for informing persons affected, a notice,

F2(a)

stating that the scheme or order has been made or confirmed F3, or as the case may be, that a draft statutory instrument containing or confirming it has been laid before the Scottish Parliament F4...

F5(b)

naming a place where a copy thereof may be inspected free of charge at all reasonable hours

F6(c)

if subsection (3) of section 143A of this Act does not apply to the F7order, scheme or instrument confirming the scheme , giving information regarding—

(i)

the date on which the scheme or order will become operative; and

(ii)

the right to challenge the validity of the scheme or order and the procedure for doing so; and

(d)

if that subsection does apply to the F8order, scheme or instrument confirming the scheme, stating that the order, scheme or instrument confirming the scheme cannot be made unless the Scottish Parliament, by resolution, approves F9a draft statutory instrument containing it.