3(1)Where a public body is satisfied that any work specified in a public body’s notice given by it has been completed, the body may give to the local authority such certificate with respect to the completion of the work and compliance with building regulations as may be prescribed (called a “public body’s final certificate”).E+W
(2)Sub-paragraphs (3) to (5) of paragraph 2 above have effect in relation to a public body’s final certificate as if any reference in those sub-paragraphs to a public body’s plans certificate were a reference to a public body’s final certificate.
(3)Where a public body’s final certificate has been given with respect to any of the work specified in a public body’s notice and that certificate has been accepted by the local authority concerned, the public body’s notice ceases to apply to that work, but the provisions of section 48(1) of this Act, as applied by section 54(4), continue, by virtue of this sub-paragraph, to apply in relation to that work as if the public body’s notice continued in force in relation to it.