Part II Supervision of Building Work etc. otherwise than by Local Authorities

Supervision of plans and work by approved inspectors

51 Final certificates.

C1F11

Where an approved inspector is satisfied that any work to which an initial notice given by him relates has been completed, he shall give to the local authority by whom the initial notice was accepted such certificate with respect to the completion of the work and the discharge of his functions as may be prescribed (called a “final certificate”).

2

Section 50(5) to (7) above has effect in relation to a final certificate as if any reference in those subsections to a plans certificate were a reference to a final certificate.

3

Where a final certificate—

a

has been given with respect to any of the work F2to which an initial notice relates, and

b

has been accepted by the local authority concerned,

the initial notice ceases to apply to that work, but section 48(1) above continues to apply, by virtue of this subsection, in relation to that work as if the initial notice continued in force in relation to it.