C1C2C3PART IX SLUM CLEARANCE

Annotations:
Modifications etc. (not altering text)
C2

Pt. IX (ss. 264–323): power to apply certain functions conferred by Housing Act 1988 (c. 50, SIF 61), s. 65(2)(a)(4)

Demolition or closing of unfit premises beyond repair at reasonable cost

267 Content of demolition F1. . . .

1

A demolition order is an order requiring that the premises—

a

be vacated within a specified period (of at least 28 days) from the date on which the order becomes operative, and

b

be demolished within six weeks after the end of that period or, if it is not vacated before the end of that period, after the date on which it is vacated or, in either case, within such longer period as in the circumstances the local housing authority consider it reasonable to specify.

2

F2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3

F3. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .