Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
[F12.(1)This paragraph and paragraph 3 apply where a customer who has served an expression of interest relating to an exempt distribution system serves on the distribution exemption holder a notice—U.K.
(a)confirming that the customer has entered into a contract with a third party supplier identified in the expression of interest for the supply of gas to premises which are connected to the exempt distribution system; and
(b)identifying that third party supplier.
(2)Within 5 working days beginning with the day on which it receives the notice served under sub-paragraph (1), the distribution exemption holder must provide any person related to it that is currently giving a supply of gas to the customer with a copy of that notice.
(3)If the distribution exemption holder has not, by the end of the 10 working day period mentioned in paragraph 1(4), served on the customer a notice under paragraph 1(4)(b), the distribution exemption holder must give the third party supplier such access to the distribution system to which the expression of interest relates as is necessary to enable the third party supplier to give a supply of gas to the customer.
(4)Access under sub-paragraph (2) must be given either—
(a)as soon as is reasonably practicable after the distribution exemption holder receives the notice served under sub-paragraph (1); or
(b)on a date agreed by the distribution exemption holder, the third party supplier and the customer in writing.
(5)Sub-paragraphs (6) to (11) apply if the distribution exemption holder has served on the customer a notice under paragraph 1(4)(b) (whether before or after the service of the notice under sub-paragraph (1)).
(6)Subject to sub-paragraph (7), the distribution exemption holder must give the third party supplier such access to its distribution system as is necessary to enable the third party supplier to give a supply of gas to the customer, and must give that access—
(a)as soon as is reasonably practicable after the end of the period of 28 working days beginning with the day on which the customer serves the notice under sub-paragraph (1); or
(b)on a date agreed by the distribution exemption holder, the third party supplier and the customer in writing.
(7)If, before the end of the period mentioned in sub-paragraph (6)(a), the distribution exemption holder takes the steps mentioned in sub-paragraph (8)—
(a)the distribution exemption holder is not required to give access in accordance with sub-paragraph (6), and
(b)sub-paragraph (9) applies.
(8)The steps mentioned in sub-paragraph (7) are—
(a)providing the third party supplier with evidence to show—
(i)that the distribution exemption holder would need to increase the capacity of its distribution system in order to give the third party supplier access to that distribution system; and
(ii)that one of the conditions in paragraph 1(5) is met; and
(b)sending a copy of the evidence to the customer.
(9)If, within the period mentioned in sub-paragraph (10), the distribution exemption holder and the third party supplier enter into a contract for the provision to the third party supplier of such access as is necessary to enable it to give a supply of gas to the customer through the distribution system, the distribution exemption holder must give access to the third party supplier in accordance with the terms of the contract.
(10)That period is—
(a)the 14 days immediately following the period mentioned in sub-paragraph (6)(a); or
(b)any longer period that the distribution exemption holder, the third party supplier and the customer may agree in writing.
(11)If, before the end of the 28 day period mentioned in sub-paragraph (6)(a), the distribution exemption holder, the third party supplier and the customer agree in writing to the extension of that period, sub-paragraphs (6) to (10) have effect as if sub-paragraph (6)(a) referred to the extended period instead of to the period of 28 working days there mentioned.]
Textual Amendments
F1Schs. 2AA, 2AB inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 20(3), Sch. 1
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: