- Latest available (Revised)
- Point in Time (01/09/1992)
- Original (As enacted)
Version Superseded: 01/03/1996
Point in time view as at 01/09/1992. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Gas Act 1986, Section 28 is up to date with all changes known to be in force on or before 12 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Subject to subsections (2) and (5) and section 29 below, where the Director is satisfied that a public gas supplier is contravening, or [F1is likely] to contravene, any relevant condition or requirement, the Director shall by a final order make such provision as is requisite for the purpose of securing compliance with that condition or requirement.
(2)Subject to subsection (5) below, where it appears to the Director—
(a)that a public gas supplier is contravening, or [F1is likely] to contravene, any relevant condition or requirement; and
(b)that it is requisite that a provisional order be made,
the Director shall (instead of taking steps towards the making of a final order) by a provisional order make such provision as appears to him requisite for the purpose of securing compliance with that condition or requirement.
(3)In determining for the purposes of subsection (2)(b) above whether it is requisite that a provisional order be made, the Director shall have regard, in particular—
(a)to the extent to which any person is likely to sustain loss or damage in consequence anything which, in contravention of the relevant condition or requirement, is likely to be done, or omitted to be done, before a final order may be made; and
(b)to the fact that the effect of the provisions of this section and section 30 below is to exclude the availability of any remedy (apart from under those provisions or for negligence) in respect of any contravention of a relevant condition or requirement.
(4)Subject to subsection (5) and section 29 below, the Director shall confirm a provisional order, with or without modifications, if—
(a)he is satisfied that the public gas supplier is contravening, or [F1is likely] to contravene, any relevant condition or requirement; and
(b)the provision made by the order (with any modifications) is requisite for the purpose of securing compliance with that condition or requirement.
(5)The Director shall not make a final order or make or confirm a provisional order if he is satisfied—
(a)that the duties imposed on him by section 4 above preclude the making or, as the case may be, the confirmation of the order[F2(aa) that the public gas supplier has agreed to take and is taking all such steps as it appears to the Director for the time being to be appropriate for the supplier to take for the purpose of securing or facilitating compliance with the condition or requirement in question;]; or
(b)that the contraventions were or the apprehended contraventions are of a trivial nature.
(6)Where the Director is satisfied as mentioned in subsection (5) above, he shall—
(a)give notice that he is so satisfied to the public gas supplier; and
(b)publish a copy of the notice in such manner as the Director considers appropriate for the purpose of bringing the matters to which the notice relates to the attention of persons likely to be affected by them.
(7)A final or provisional order—
(a)shall require the public gas supplier (according to the circumstances of the case) to do, or not to do, such things as are specified in the order or are of a description so specified;
(b)shall take effect at such time, being the earliest practicable time, as is determined by or under the order; and
(c)may be revoked at any time by the Director.
(8)In this section and sections 29 and 30 below—
“final order” means an order under this section other than a provisional order;
“provisional order” means an order under this section which, if not previously confirmed under subsection (4) above, will cease to have effect at the end of such period (not exceeding three months) as is determined by or under the order;
“relevant condition”, in relation to a public gas supplier, means any condition of his authorisation;
“relevant requirement”, in relation to a public gas supplier, means any requirement imposed on him by or under section 9(1) or (2), 10(1), 11(4), 12(1) [F314(1) or (3), 14A(4) or 15B] above [F4or section 33B, 33D or 33E below] or any provision of paragraphs 1 to 4 and 14 of Schedule 5 to this Act.
Textual Amendments
F1Words in s. 28(1)(2)(4)(a) substituted (1.7.1992) by Competition and Service (Utilities) Act 1992 (c. 43), s. 48(2); Commencement Order No. 1 made on 29.5.1992, art. 3, Sch. Pt.I.
F2S. 28(5)(aa) inserted (1.7.1992) by Competition and Service (Utilities) Act 1992 (c. 43), s. 48(3); Commencement Order No. 1 made on 29.5.1992, art. 3, Sch. Pt. I.
F3Words in s. 28(8) substituted (1.7.1992) by Competition and Service (Utilities) Act 1992 (c. 43), s. 56(6), Sch. 1 para. 6(a); Commencement Order No. 1 made on 29.5.1992, art. 3, Sch. Pt. I.
F4Words in s. 28(8) inserted (1.7.1992) by Competition and Service (Utilities) Act 1992 (c. 43), s. 56(6), Sch. 1 para. 6(b); Commencement Order No. 1 made on 29.5.1992, art. 3, Sch. Pt. I.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: