SCHEDULES

SCHEDULE 7E+W Protective Provisions

Part IE+W Protection of Port Authority and River Users

3(1)Not less than 56 days before commencing any operations for the construction of any tidal work, or operations for the maintenance or improvement of any such work affecting the river, the Secretary of State shall submit to the Port Authority for their approval plans of the work or (as the case may be) proposed operations and the proposed timetable for the operations.E+W

(2)In sub-paragraph (1) above—

(3)The Secretary of State shall supply to the Port Authority with the plans and proposed timetable such relevant hydraulic information as may be available to the Secretary of State and is not in the possession of the Port Authority.

(4)The Secretary of State shall submit to the Port Authority such further particulars available to him with respect to the work and the proposed operations as the Port Authority may, within 28 days of the submission of the plans and proposed timetable, reasonably require.

(5)The Port Authority’s approval of the plans and proposed timetable submitted under sub-paragraph (1) above shall not be unreasonably withheld; and if within 56 days after the submission of the plans and proposed timetable the Port Authority have not approved or disapproved them, they shall be deemed to have approved them.