Print Options
PrintThe Whole
Act
PrintThe Whole
Schedule
PrintThe Whole
Part
PrintThis
Section
only
Changes over time for: Paragraph 3


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 01/04/1996.
Changes to legislation:
There are currently no known outstanding effects for the Dartford-Thurrock Crossing Act 1988, Paragraph 3.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
3(1)Not less than 56 days before commencing the construction of the specified works, the Secretary of State shall submit to the Railways Board for their approval plans of the works and such further particulars available to him as the Railways Board may, within 28 days of the submission of the plans, reasonably require.E+W
(2)The Railways Board’s approval of plans submitted under sub-paragraph (1) above shall not be unreasonably withheld; and if within 56 days after the submission of the plans the Railways Board have not approved or disapproved them, they shall be deemed to have approved them.