Completion noticesE+W
1(1)If it comes to the notice of a [F1billing authority] that the work remaining to be done on a new building in its area is such that the building can reasonably be expected to be completed within 3 months, the authority shall serve a notice under this paragraph on the owner of the building as soon as is reasonably practicable unless the valuation officer otherwise directs in writing.E+W
(2)If it comes to the notice of a [F1billing authority] that a new building in its area has been completed, the authority may serve a notice under this paragraph on the owner of the building unless the valuation officer otherwise directs in writing.
(3)A [F1billing authority] may withdraw a notice under this paragraph by serving on the owner of the building to which the notice relates a subsequent notice under this paragraph.
(4)Where an appeal under paragraph 4 below has been brought against a notice under this paragraph, the power conferred by sub-paragraph (3) above shall only be exercisable with the consent in writing of the owner of the building to which the notice relates.
(5)The power conferred by sub-paragraph (3) above shall cease to be exercisable in relation to a notice under this paragraph once a day has been determined under this Schedule as the completion day in relation to the building to which the notice relates.
(6)In this Schedule “completion notice” means a notice under this paragraph.
Textual Amendments
F1Words in Sch. 4A para. 1(1)-(3) substituted (6.3.1992) by 1992 c. 14, s. 117(1), Sch. 13 para. 83(1) (with s. 118(1)(2)(4))
2(1)A completion notice shall specify the building to which it relates and state the day which the authority proposes as the completion day in relation to the building.E+W
(2)Where at the time a completion notice is served it appears to the authority that the building to which the notice relates is not completed, the authority shall propose as the completion day such day, not later than 3 months from and including the day on which the notice is served, as the authority considers is a day by which the building can reasonably be expected to be completed.
(3)Where at the time a completion notice is served it appears to the authority that the building to which the notice relates is completed, the authority shall propose as the completion day the day on which the notice is served.