- Latest available (Revised)
- Point in Time (01/04/2007)
- Original (As enacted)
Version Superseded: 26/12/2023
Point in time view as at 01/04/2007. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
Local Government Finance Act 1988, Section 46A is up to date with all changes known to be in force on or before 22 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Schedule 4A below (which makes provision with respect to the determination of a day as the completion day in relation to a new building) shall have effect.
(2)Where—
(a)a completion notice is served under Schedule 4A below, and
(b)the building to which the notice relates is not completed on or before the relevant day,
then for the purposes of section 42 above and Schedule 6 below the building shall be deemed to be completed on that day.
(3)For the purposes of subsection (2) above the relevant day in relation to a completion notice is—
(a)where an appeal against the notice is brought under paragraph 4 of Schedule 4A below, the day stated in the notice, and
(b)where no appeal against the notice is brought under that paragraph, the day determined under that Schedule as the completion day in relation to the building to which the notice relates.
(4)Where—
(a)a day is determined under Schedule 4A below as the completion day in relation to a new building, and
(b)the building is not occupied on that day,
it shall be deemed for the purposes of section 45 above to become unoccupied on that day.
(5)Where—
(a)a day is determined under Schedule 4A below as the completion day in relation to a new building, and
(b)the building is one produced by the structural alteration of an existing building,
the hereditament which comprised the existing building shall be deemed for the purposes of section 45 above to have ceased to exist, and to have been omitted from the list, on that day.
(6)In this section—
(a)“building” includes part of a building, and
(b)references to a new building include references to a building produced by the structural alteration of an existing building where the existing building is comprised in a hereditament which, by virtue of the alteration, becomes, or becomes part of, a different hereditament or different hereditaments.]
Textual Amendments
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: