Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Section 13(2).
1E+W+SThe following provisions of this Schedule apply where a relevant undertaker is proposing to execute any undertaker’s works which involve or are likely to involve a temporary or permanent alteration of any system apparatus of a licensed operator of a driver information system kept installed in, upon, under, over, along or across any land.
2(1)The relevant undertaker shall, not less than 10 days before the works are commenced, give the operator a notice specifying the nature of the undertaker’s works, the alteration or likely alteration involved and the time and place at which the works will be commenced.E+W+S
(2)This paragraph shall not apply in relation to any emergency works of which the relevant undertaker gives the operator notice as soon as practicable after commencing the works.
3E+W+SWhere a notice has been given under paragraph 2 above by a relevant undertaker to the operator, the operator may within the period of 10 days beginning with the giving of the notice give the relevant undertaker a counter-notice which may state either—
(a)that the operator intends himself to make any alterations made necessary or expedient by the proposed undertaker’s works; or
(b)that he requires the undertaker in making any such alteration to do so under the supervision and to the satisfaction of the operator.
4E+W+SWhere a counter-notice given under paragraph 3 above states that the operator intends himself to make any alteration—
(a)the operator shall (subject to paragraph 6 below) have the right, instead of the relevant undertaker, to execute any works for the purpose of making that alteration; and
(b)any expenses incurred by the operator in or in connection with the execution of those works and the amount of any loss or damage sustained by the operator in consequence of the alteration shall be recoverable by the operator from the undertaker in any court of competent jurisdiction.
5E+W+SWhere a counter-notice given under paragraph 3 above states that any alteration is to be made under the supervision and to the satisfaction of the operator—
(a)the relevant undertaker shall not make the alteration except as required by the notice or under paragraph 6 below; and
(b)any expenses incurred by the operator in or in connection with the provision of that supervision and the amount of any loss or damage sustained by the operator in consequence of the alteration shall be recoverable by the operator from the undertaker in any court of competent jurisdiction.
6E+W+SWhere—
(a)no counter-notice is given under paragraph 3 above, or
(b)the operator, having given a counter-notice falling within that paragraph, fails within a reasonable time to make any alteration made necessary or expedient by the proposed undertaker’s works or, as the case may be, unreasonably fails to provide the required supervision,
the relevant undertaker may himself execute works for the purpose of making the alteration or, as the case may be, may execute such works without the supervision of the operator; but in either case the undertaker shall execute the works to the satisfaction of the operator.
7(1)If the relevant undertaker or any of his agents—E+W+S
(a)executes any works without the notice required by paragraph 2 above having been given, or
(b)fails without reasonable excuse to comply with any reasonable requirement of the operator under this Schedule,
he shall be guilty of an offence.
(2)A person guilty of an offence under this paragraph shall be liable on summary conviction to a fine which—
(a)if the service provided by the operator’s system is interrupted by the works or failure, shall not exceed level 4 on the standard scale; and
(b)if that service is not so interrupted, shall not exceed level 3 on the standard scale.
8In this Schedule—
“relevant undertaker” means—
(a)any person or authority authorised by or under any Act (whether public general or local) to carry on any railway, tramway, road transport, water transport, canal, inland navigation, dock, harbour, pier or lighthouse undertaking;
(b)any person to whom the telecommunications code is applied by a licence under section 7 of the M1Telecommunications Act 1984 authorising him to run a telecommunication system;
(c)any public gas supplier (within the meaning of Part I of the M2Gas Act 1986);
(d)any holder of a licence under Part I of the M3Electricity Act 1989 who is entitled to exercise any power conferred by paragraph 1 or 2 of Schedule 4 to that Act;
(e)The National Rivers Authority or any water undertaker or sewerage undertaker;
(f)any other licensed operator of a driver information system; or
(g)any person to whom this Schedule is applied by any Act passed after this Act;
“undertaker’s works” means—
(a)in relation to a relevant undertaker falling within paragraph (a) above, any works which he is authorised to execute for the purpose of, or in connection with, the carrying on by him of the undertaking mentioned in that paragraph;
(b)in relation to a relevant undertaker falling within paragraph (b) above, any works which he is authorised to execute for the purposes of, or in connection with, a telecommunication system run by him;
(c)in relation to a relevant undertaker falling within paragraph (c) above, any works which he is authorised to execute for the purposes of, or in connection with, his supplying gas as a public gas supplier;
(d)in relation to a relevant undertaker falling within paragraph (d) above, any works which he is authorised to execute for any purpose connected with the carrying on of the activities which he is authorised by his licence to carry on;
(e)in relation to a relevant undertaker falling within paragraph (e) above, any works which that Authority or undertaker has power to execute for purposes connected with the carrying on of its functions;
(f)in relation to a relevant undertaker falling within paragraph (f) above, any works which he is authorised to execute for the purposes of, or in connection with, a driver information system operated by him; and
(g)in relation to a relevant undertaker falling within paragraph (g) above, the works for the purposes of which this Schedule is applied to him.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: