F1 SCHEDULES
C1F2SCHEDULE 6AProvisions imposing obligations enforceable as relevant requirements
Sch. 6A: power to amend conferred (18.12.2013) by Energy Act 2013 (c. 32), ss. 38(c), 156(3)
All licence holders
1
The following are relevant provisions in relation to all licence holders F4(except the holder of a smart meter communication licence) —
a
sections 32 to 32M;
b
section 42C;
c
section 25(5) of the Consumers, Estate Agents and Redress Act 2007 (directions to comply with requirements under section 24 of that Act);
F24ca
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
d
in the Electricity Regulation—
i
F8Article 50(5) (provision of information relating to the transmission system etc),
ii
F9Article 16(10) and (12) (duties relating to intended use of capacity);
F10e
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
g
in the Transparency Regulation—
i
Article 4 (submission and publication of data),
ii
Article 6 (information on total load),
iii
Article 7 (information relating to the unavailability of consumption units),
iv
Article 8 (year-ahead forecast margin),
v
Article 9 (transmission infrastructure),
vi
Article 10 (information relating to the unavailability of transmission infrastructure),
vii
Article 11 (information relating to the estimation and offer of cross zonal capacities),
viii
Article 12 (information relating to the use of cross zonal capacities),
ix
Article 13 (information relating to congestion management measures),
x
Article 14 (forecast generation),
xi
Article 15 (information relating to the unavailability of generation and production units),
xii
Article 16 (actual generation),
xiii
Article 17 (balancing).
Generation licence holders
2
F12Article 50(6) of the Electricity Regulation (duty to keep specified information at the disposal of the Authority) is a relevant provision in relation to the holder of a generation licence.
Transmission licence holders
3
The following are relevant provisions in relation to all holders of a transmission licence—
a
section 9;
b
sections 26 to 29 of the Energy Act 2010 (adjustment of charges to help disadvantaged groups of customers).
Persons required to be certified as to independence
4
The following are relevant provisions in relation to a person who holds a transmission licence or an interconnector licence and is required to be certified under section 10D—
a
section 10A;
b
section 10B(4) and (6);
c
section 10J(2) and (4);
F16d
in the Electricity Regulation—
i
Article 6(13) (duties in respect of publication of information),
ii
Article 7 (duties in relation to day-ahead and intraday markets),
iii
Article 9 (duties in relation to forward markets),
iv
Article F1916(1), (2), (4), (6), (10) and (11) (duties concerning capacity allocation and congestion management),
F20v
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
vi
Article 18(1), (3), (4) and (6) (duties relating to charges for access to networks, use of network and reinforcement),
vii
Article 19(2) and (3) (congestion income),
F21viii
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F21ix
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F21x
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F21xi
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
xii
Article 50(1) to (4) (duties relating to publication of specified information),
F22xiii
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
da
Article 8 (publication on the internet) of the Electricity Transmission System Operation Regulation;
db
in the Network Code on Electricity Emergency and Restoration—
i
Article 36(2) (publication of rules for suspension and restoration of market activities),
ii
Article 39(1) duty to develop and publish rules for settlement in case of suspension of market activities);
F15e
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
f
Article 2 of the ITC Regulation (duty to apply access charges in accordance with guidelines);
F23g
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F14h
in the Transparency Regulation—
i
Article 6 (information on total load),
ii
Article 7 (information relating to the unavailability of consumption units),
iii
Article 8 (year-ahead forecast margin),
iv
Article 9 (transmission infrastructure),
v
Article 10 (information relating to the unavailability of transmission infrastructure),
vi
Article 11 (information relating to the estimation and offer of cross zonal capacities),
vii
Article 12 (information relating to the use of cross zonal capacities),
viii
Article 13 (information relating to congestion management measures),
ix
Article 14 (forecast generation),
x
Article 15 (information relating to the unavailability of generation and production units),
xi
Article 16 (actual generation),
xii
Article 17 (balancing).
Distribution licence holders
5
The following are relevant provisions in relation to the holder of a distribution licence—
a
section 9;
b
sections 16 to 23;
c
section 40A;
d
sections 42 and 42A;
e
section 42AB;
f
sections 43, 46 and 47 of the Consumers, Estate Agents and Redress Act 2007 (complaints);
g
sections 26 to 29 of the Energy Act 2010 (adjustment of charges to help disadvantaged groups of consumers).
Supply licence holders
6
The following are relevant provisions in relation to the holder of a supply licence—
a
section 40;
b
sections 42 and 42A;
c
section 42AB;
d
sections 43, 46 and 47 of the Consumers, Estate Agents and Redress Act 2007 (complaints);
e
paragraph 3(4) of Schedule 2ZA;
f
in the Energy Act 2010—
i
section 9 (schemes for reducing fuel poverty),
ii
section 11 (reconciliation mechanism),
iii
sections 26 to 29 (adjustment of charges to help disadvantaged groups of consumers).
F30g
h
section 22 of the Energy Prices Act 2022.
Distribution exemption holders
7
The following paragraphs of Schedule 2ZA are relevant provisions in relation to a distribution exemption holder—
a
paragraph 1(3), (4) and (6) to (8);
b
paragraph 2(2) to (4), (6) and (9);
c
paragraph 3(6), (12)(a) and (13);
d
paragraph 5(1) to (4), (6), (8) and (9);
e
paragraph 6(2);
f
paragraph 7(2) and (4);
g
paragraph 8(4) and (9);
h
paragraph 9;
i
paragraph 13(2);
j
paragraph 14(5), (6), (9) and (12);
h
paragraph 15(1).
Supply exemption holders
8
The following are relevant provisions in relation to a supply exemption holder—
a
paragraph 3(4) of Schedule 2ZA;
b
the following paragraphs of Schedule 2ZB—
i
paragraph 1(2), (3), (6) and (7),
ii
paragraph 2(6),
iii
paragraph 3(1) and (3),
iv
paragraph 4,
v
paragraph 5(1), (6) and (8),
vi
paragraph 6,
vii
paragraph 7.
Electricity undertakings which are relevant producers or suppliers
9
The following are relevant provisions in relation to an electricity undertaking which is a relevant producer or supplier—
a
section 10B(5) and (6);
b
section 10J(3) and (4);
c
section 8D(5) and (6) of the Gas Act 1986 (duties concerning supply of information for application for certification as to independence);
d
section 8L(3) and (4) of that Act (duties concerning supply of information for review of certification as to independence);
F26e
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F27f
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F3Smart meter communication licence holders
Sch. 6A para. 9A and cross-heading inserted (19.9.2012) by The Electricity and Gas (Smart Meters Licensable Activity) Order 2012 (S.I. 2012/2400), art. 16(3)
9A
The following are relevant provisions in relation to the holder of a smart meter communication licence—
a
section 42C; and
b
section 25(5) of the Consumers, Estate Agents and Redress Act 2007 (directions to comply with requirements under section 24 of that Act).
F6Nominated electricity market operators
Sch. 6A para. 9B inserted (24.4.2017) by The Electricity and Gas (Internal Markets) Regulations 2017 (S.I. 2017/493), regs. 1(1), 6(3)
F289B
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F7Interpretation
Sch. 6A para. 10 and cross-heading substituted (25.2.2020) by The Electricity and Gas (Internal Markets) Regulations 2020 (S.I. 2020/96), regs. 1, 3(9)(e)
10
In this Schedule—
“the Electricity Balancing Regulation” means Commission Regulation (EU) 2017/2195 of 23 November 2017 establishing a guideline on electricity balancing;
“the Electricity Transmission System Operation Regulation” means Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation;
F29...
“the ITC Regulation” means Commission Regulation (EU) 2010/838 of 23 September 2010 on laying down guidelines relating to the inter-transmission system operator compensation mechanism and a common regulatory approach to transmission charging;
“the Network Code on Electricity Emergency and Restoration” means Commission Regulation (EU) 2017/2196 of 24 November 2017 establishing a network code on electricity emergency and restoration;
“the Transparency Regulation” means Commission Regulation (EU) No 543/2013 of 14 June 2013 on submission and publication of data in electricity markets and amending Annex I to Regulation (EC) No 714/2009 of the European Parliament and of the Council.
F511
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Sch. 6A inserted (10.11.2011) by The Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), regs. 1(1), 39(5), Sch. 4 (as amended (14.1.2015) by S.I. 2014/3332, regs. 1(1), 7)