Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Nothing in section 16(1) requires an electricity distributor to make a connection if and to the extent that—
(a)he is prevented from doing so by circumstances not within his control;
(b)circumstances exist by reason of which his doing so would or might involve his being in breach of regulations under section 29, and he has taken all such steps as it was reasonable to take both to prevent the circumstances from occurring and to prevent them from having that effect; or
(c)it is not reasonable in all the circumstances for him to be required to do so.
(2)Without prejudice to the generality of subsection (1) an electricity distributor is not required to make a connection if—
(a)making the connection involves the distributor doing something which, without the consent of another person, would require the exercise of a power conferred by any provision of Schedule 3 or 4;
(b)the distributor’s licence does not provide for that provision to have effect in relation to him; and
(c)any necessary consent has not, at the time the request is made, been given.
(3)Subsection (1)(c) does not permit an electricity distributor to disconnect any premises or distribution system to which a connection is being maintained by him unless the distributor gives—
(a)where the connection is to premises, to the occupier or to the owner if the premises are not occupied;
(b)where the connection is to another distribution system, to the person who is authorised by a licence or exemption to run that system,
not less than seven working days’ notice of his intention to disconnect the premises or distribution system.]
Textual Amendments
F1Ss. 16, 16A, 17 and cross-heading substituted for ss. 16, 17 (1.10.2001) by 2000 c. 27, s. 44; S.I. 2001/3266, art. 2, Sch. (subject to transitional provisions in arts. 3-20)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: