Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)A renewables obligation order may make provision generally in relation to the renewables obligation.
(2)A renewables obligation order may, in particular, specify—
(a)how the number of renewables obligation certificates required to be produced by an electricity supplier in respect of the amount of electricity supplied by it to customers in the relevant part of Great Britain during a specified period is to be calculated;
(b)different obligations for successive periods of time;
(c)that renewables obligation certificates issued in respect of electricity generated—
(i)using specified descriptions of renewable sources,
(ii)by specified descriptions of generating stations,
(iii)in specified ways, or
(iv)in other specified cases or circumstances,
are to count towards discharging an electricity supplier's obligation only up to a specified number, or a specified proportion, of the certificates required to be produced to discharge the obligation;
(d)that a specified number, or a specified proportion, of the renewables obligation certificates produced by an electricity supplier when discharging its renewables obligation must be certificates in respect of electricity generated—
(i)using specified descriptions of renewable sources,
(ii)by specified descriptions of generating station,
(iii)in specified ways, or
(iv)in other specified cases or circumstances;
(e)how the amount of electricity supplied by an electricity supplier to customers in the relevant part of Great Britain during a specified period is to be calculated;
(f)that specified information, or information of a specified nature, is to be given to the Authority;
(g)the form in which such information is to be given and the time by which it is to be given.
(3)A renewables obligation certificate may count once only towards the discharge of the renewables obligation.
(4)Except as provided by a renewables obligation order, a renewables obligation certificate counts towards discharging the renewables obligation regardless of whether the order under which it is issued is made by the Secretary of State or the Scottish Ministers.
(5)A renewables obligation order may specify that the only renewables obligation certificates which count towards discharging the renewables obligation are certificates which are issued—
(a)in respect of electricity supplied to customers in the relevant part of Great Britain, or
(b)in respect of electricity used in a permitted way (within the meaning of section 32B(9) and (10)) in that part of Great Britain.
(6)A renewables obligation order may, in relation to any specified period (“the current period”)—
(a)provide that renewables obligation certificates in respect of electricity supplied in a later period may, when available, be counted towards discharging the renewables obligation for the current period;
(b)provide that renewables obligation certificates in respect of electricity supplied in the current period may, in a later period, be counted towards discharging the renewables obligation for that period;
(c)specify how much later the later period referred to in paragraph (a) or (b) may be;
(d)specify a maximum proportion of the renewables obligation for any period which may be discharged as mentioned in paragraph (a) or (b);
(e)specify a maximum proportion, or maximum number of, the renewables obligation certificates issued in respect of electricity supplied in any period which may be counted towards discharging the renewables obligation for a different period.
(7)For the purposes of subsection (6) a certificate which certifies that electricity has been used in a permitted way (within the meaning of section 32B(9) and (10)) in a particular period is to be treated as if it were a certificate which certifies that electricity has been supplied in that period.]
Textual Amendments
F1Ss. 32-32M substituted for (26.11.2008 for specified purposes, 1.4.2009 in so far as not already in force) by Energy Act 2008 (c. 32), ss. 37, 110(1)(a) (with s. 38); S.I. 2009/45, art. 3(a) (with art. 5)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Part you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Part you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: