Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)A certificate purchase order may (subject to subsection (3)) provide for the Authority to issue from time to time, in accordance with such criteria (if any) as are specified in the order, a certificate (“a GB certificate”) to—
(a)the operator of a generating station, or
(b)if the order so provides, a person of any other description specified in the order.
(2)A GB certificate is to certify—
(a)the matters within subsection (4) or (5), or
(b)if the order provides that a certificate may certify the matters within subsection (6), (7), (8) or (9), the matters within that subsection.
(3)A GB certificate certifying that an amount of electricity has been generated from renewable sources in any period may not be issued if—
(a)a renewables obligation order is in force, and
(b)a renewables obligation certificate has been, or could be, issued under the order in respect of the generation in that period of the same electricity.
(4)The matters within this subsection are—
(a)that the generating station, or, in the case of a certificate issued otherwise than to the operator of a generating station, a generating station specified in the certificate, has generated from renewable sources the amount of electricity stated in the certificate, and
(b)that the electricity has been supplied by an electricity supplier to customers in Great Britain.
(5)The matters within this subsection are—
(a)that the generating station, or, in the case of a certificate issued otherwise than to the operator of a generating station, a generating station specified in the certificate, has generated from renewable sources the amount of electricity stated in the certificate,
(b)that the generating station in question is not in Northern Ireland, and
(c)that the electricity has been supplied by a Northern Ireland supplier to customers in Northern Ireland.
(6)The matters within this subsection are—
(a)that two or more generating stations have, between them, generated from renewable sources the amount of electricity stated in the certificate, and
(b)that the electricity has been supplied by an electricity supplier to customers in Great Britain.
(7)The matters within this subsection are—
(a)that two or more generating stations have, between them, generated from renewable sources the amount of electricity stated in the certificate,
(b)that none of them is a generating station in Northern Ireland, and
(c)that the electricity has been supplied by a Northern Ireland supplier to customers in Northern Ireland.
(8)The matters within this subsection are—
(a)that the generating station, or, in the case of a certificate issued otherwise than to the operator of a generating station, a generating station specified in the certificate, has generated from renewable sources the amount of electricity stated in the certificate, and
(b)that the electricity has been used in a permitted way.
(9)The matters within this subsection are—
(a)that two or more generating stations have, between them, generated from renewable sources the amount of electricity stated in the certificate, and
(b)that the electricity has been used in a permitted way.
(10)For the purposes of subsections (8) and (9), electricity generated by a generating station, or generating stations, of any description is used in a permitted way if—
(a)it is used in one of the ways mentioned in subsection (11), and
(b)that way is specified in the order as a permitted way—
(i)in relation to all generating stations, or
(ii)in relation to generating stations of that description.
(11)Those ways are—
(a)being consumed by the operator of the generating station or generating stations by which it was generated;
(b)being supplied to customers in Great Britain through a private wire network;
(c)being provided to a distribution system or a transmission system in circumstances in which its supply to customers cannot be demonstrated;
(d)being used, as respects part, as mentioned in one of paragraphs (a), (b) or (c) and as respects the remainder—
(i)as mentioned in one of the other paragraphs, or
(ii)as respects part, as mentioned in one of the other paragraphs and, as respects the remainder, as mentioned in the other;
(e)being used, as respects part, as mentioned in paragraph (a), (b), (c) or (d) and, as respects the remainder, by being supplied by an electricity supplier to customers in Great Britain or by a Northern Ireland supplier to customers in Northern Ireland, or both.
(12)Subsection (11) of section 32B (meaning of supply of electricity through a private wire network) applies for the purposes of subsection (11)(b) as it applies for the purposes of subsection (10)(b) of that section.]
Textual Amendments
F1Ss. 32N-32Z2 inserted (18.2.2014) by Energy Act 2013 (c. 32), ss. 56(2), 156(2)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Part you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Part you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: